Multi Family

Multi Family Aluminum w/ New Footing

Screen enclosures, pool cages, carports, aluminum pergolas including new footing construction

Last updated: Apr 20, 2026

Section 1

Required Documents

Submit these with your initial project package.

Always required

  • Construction Plans Sealed by a Florida Registered Design Professional
    Construction plans sealed by a Florida-registered design professional showing aluminum structure layout and framing, including footing and foundation engineering details.
  • Site Plan / Survey
    Site plan or survey showing property boundaries, setbacks, and structure footprint.

Courtesy screen

Courtesy screen on every plan review

Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.

  1. #01Plan and document coordination

    Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.

    FBC-B 107.2.1
  2. #02Zoning and site coordination

    Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.

  3. #03Floodplain coordination

    Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.

  4. #04Fire-authority coordination

    Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.

Section 2

Approval criteria for this project type

These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.

BuildingRequired

  1. #01Design wind speed & exposureLife Safety

    Structural drawings must declare design wind speed (Vult) and exposure category matching the jurisdiction's wind speed map.

    FBC-R R301.2.1ASCE 7-22
  2. #02Footing / foundation designLife Safety

    Footing or foundation design must show dimensions, reinforcement, depth, and connection to the structure above.

    FBC-R R403FBC-B 1809
  3. #03Florida product approvalCode

    Florida product approval (FL#) or Miami-Dade NOA must be listed for regulated products (fenestration, structural panels, covering systems).

    FBC-B 1708FBC-R R301.2.1.2
  4. #04Engineer of record sealDocumentation

    Structural drawings must bear a current Florida-licensed engineer's seal and signature.

    Florida Statutes Chapter 471FBC-B 107.3.5

Section 3

Inspection Walkthrough

Inspections are listed in their typical phase order. Your FCC inspector will confirm which apply to your project. Call (772) 222-6679 with questions.

Building

Phase #1

Footing, Slab, UFER

Required
  1. Footing dimensionsCritical

    Verify footing depth and width match approved plans

    FBC-R R403.1FBC-R R403.1.1
  2. Rebar size and placementCritical

    Verify rebar size, spacing, and placement per approved plans

    FBC-R R403.1
  3. Footing layout and alignment

    Verify footing layout matches approved site plan dimensions

    FBC-B 110.3
  4. Clean and debris-free excavation

    Confirm excavation is free of standing water, loose soil, and debris before pour

    FBC-R R403.1
Phase #2

Final Building

RequiredTypical Final
  1. Base rail attachment and tapcon spacingCritical

    Verify base rail is secured with tapcons at correct spacing per plans

    FBC-B 2002.1FBC-B 2002.4
  2. Post to base connectionCritical

    Verify structural connection of posts to base rail

    FBC-B 2002.1
  3. Post to roof beam connectionCritical

    Verify structural connection of posts to roof beams

    FBC-B 2002.1
  4. Gusset connectionsCritical

    Verify gusset plates are installed at structural joints per plans

    FBC-B 2002.1FBC-B 2002.4
  5. Beam to gutter connectionCritical

    Verify beams are properly connected to gutter system

    FBC-B 2002.1
  6. Gutter clips

    Verify gutter clips are installed at proper intervals

    FBC-B 2002.1
  7. Overall structureCritical

    Verify overall shape and construction matches approved plans

    FBC-B 2002.4
  8. Screen door opening mechanism height

    Verify door latch/opening mechanism is at 54 inch height where pool barrier applies

    NEC 680.26FBC-R R303
  9. Pool equipment bonding

    If pool equipment is present, verify bonding wire at pool equipment and at structure

    NEC 680.26
  10. Elite roof panel sealing

    If elite (solid) roof panels are present, verify sealing is complete

    FBC-B 2002.5