- #01Plan and document coordination
Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.
FBC-B 107.2.1 - #02Zoning and site coordination
Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #03Floodplain coordination
Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #04Fire-authority coordination
Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
Single Family Generator Install
Last updated: Apr 20, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Equipment SpecificationsManufacturer specifications for the generator including capacity, fuel type, and output rating
- Electrical Load CalculationsElectrical load calculations showing generator capacity relative to the loads it will serve
- Site PlanSite plan showing generator placement, clearances, and fuel supply routing
Courtesy screen
Courtesy screen on every plan review
Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.
Section 2
Approval criteria for this project type
These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.
ElectricalRequired
- #01Generator disconnect, transfer switch, and labelingLife Safety
Standby generator installation requires approved transfer switch, disconnect, and required labeling per NEC 702 / 445.
NEC 445NEC 702NEC 230.82 - #02Grounding and bondingLife Safety
Grounding electrode, equipment grounding, and bonding per NEC Article 250.
NEC 250 - #03Construction-document clarity — generator installationDocumentation
The submitted documents must clearly identify the standby generator, transfer equipment, and electrical connections so FCC can review this mandatory single-family electrical trade as part of the one residential plan review.
FBC-B 107.2.1
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your FCC inspector will confirm which apply to your project. Call (772) 222-6679 with questions.
Electrical
Rough Electrical
Required- Generator pad and placementCritical
Verify generator is placed on approved pad with required clearances from structure, openings, and property lines
NEC 445.10FBC-M 304.1 - Electrical connection and transfer switchCritical
Verify transfer switch installation, wire sizing, and connection to main panel per plans
NEC 702.4NEC 445.13 - Fuel line installationCritical
Verify gas line sizing, routing, and connections per plans (if natural gas/propane)
FBC-FG 401.1 - GroundingCritical
Verify generator grounding per NEC requirements
NEC 250.34
Final Electrical
RequiredTypical Final- Generator operational testCritical
Verify generator starts, runs, and transfers load properly
NEC 702.4 - Transfer switch operationCritical
Verify automatic transfer switch engages and disengages properly
NEC 702.4 - Labeling and signageCritical
Verify all required labels at generator, transfer switch, and main panel
NEC 702.7NEC 445.11 - Sound and vibration
Verify generator meets any local noise ordinance requirements
FBC-B 110.3
