- #01Plan and document coordination
Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.
FBC-B 107.2.1 - #02Zoning and site coordination
Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #03Floodplain coordination
Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #04Fire-authority coordination
Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
Commercial Battery Storage Installation
Stationary battery energy storage at commercial, apartment, or condo property, with or without solar.
Last updated: Sep 29, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Electrical PlansElectrical plans for the installation. A licensed electrical contractor may prepare unsealed plans for a system it installs within the limits of F.S. 471.003(2)(h). Plans prepared by an engineer carry the engineer's seal.
- Equipment SpecificationsManufacturer spec sheet with the UL 9540 listing and kWh capacity
- Installation Location PlanPlan showing the installation location and clearances
Courtesy screen
Courtesy screen on every plan review
Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.
Section 2
Approval criteria for this project type
These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.
ElectricalConditional review scope
- #01Grounding and bondingLife Safety
Grounding electrode, equipment grounding, and bonding per NEC Article 250.
NEC 250 - #02Energy storage system listing and installationLife Safety
The energy storage system must be listed to UL 9540 and installed per NEC Article 706, including its inverter connections and disconnecting means.
NEC 706UL 9540 - #03Service size and load calculationCode
Electrical service and feeder sizing supported by NEC Article 220 load calculation.
NEC 220NEC 230
Items marked Conditional review scope are non-blocking. Per FBC 107.3.5, plan review isn't required for these scopes — FCC reviews them when the building department requests it or the client wants the extra set of eyes.
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your own inspection list comes from your approved plans. Inspections marked “If in scope” apply only when your plans include that work. Call (772) 222-6679 with questions.
Electrical
Electrical Rough-In
- ESS listing and placementCritical
Match listed ESS, mounting, location and ventilation to approved plans and manufacturer instructions.
NEC 706.5NEC 706.20 - Working space and wiringCritical
Show required working space and exposed conductor/raceway route against plans.
NEC 110.26 - ESS disconnect roughCritical
Show disconnect location and rough connections before concealment.
NEC 706.15
Electrical Final
Typical Final- Listed ESS and labelsCritical
Verify listed ESS model and installed system match approved plans.
NEC 706.5 - ESS disconnect and markingsCritical
Verify accessible disconnect, permanent marking, and open/closed indication.
NEC 706.15 - Working space and ventilationCritical
Show clear working space and technology-appropriate ventilation as approved.
NEC 706.20NEC 110.26 - System commissioningCritical
Demonstrate normal ESS status and shutdown/restart according to manufacturer and approved commissioning procedure.