- #01Plan and document coordination
Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.
FBC-B 107.2.1 - #02Zoning and site coordination
Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #03Floodplain coordination
Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #04Fire-authority coordination
Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
Commercial Detached Garage
New detached garage serving commercial, apartment, or condo property. Electrical inspections apply only when wiring is included.
Last updated: Sep 29, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Construction PlansConstruction plans for the work. Plans prepared by a Florida-registered architect or engineer carry that professional's seal. Plans prepared by a contractor or owner are accepted without a seal unless Florida law or the building department requires professional plans.
- Product ApprovalsFlorida Product Approvals for regulated components
- Site Plan / SurveySite plan or survey showing property boundaries, setbacks, and construction footprint
Conditional
- Energy Compliance FormsEnergy compliance documentationWhenRequired if garage includes conditioned space
- Truss Engineering OR Truss Deferral AffidavitTruss engineering package, conventional framing per FBC, or a truss deferral letter requesting deferred submittal of truss engineering.WhenRequired only when structure uses pre-engineered trusses and truss engineering is not shown in the plan set; satisfied by truss engineering in plan set OR conventional framing per FBC OR a truss deferral letter.
Courtesy screen
Courtesy screen on every plan review
Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.
Section 2
Approval criteria for this project type
These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.
BuildingRequired
- #01Design wind speed & exposureLife Safety
Structural drawings must declare design wind speed (Vult) and exposure category matching the jurisdiction's wind speed map.
FBC-B 1609ASCE 7-22 - #02Footing / foundation designLife Safety
Footing or foundation design must show dimensions, reinforcement, depth, and connection to the structure above.
FBC-B 1809 - #03Detached-structure setbackLife Safety
Exterior walls must have the fire-resistance rating and opening protection required for their fire separation distance (FBC-B 705.5 / 705.8). Zoning setbacks are the jurisdiction's review.
FBC-B 705.5FBC-B 705.8 - #04Engineer of record seal, when engineeredDocumentation
When a Florida engineer prepared the structural drawings, the document carries that engineer's seal and signature. Contractor- or owner-prepared structural drawings need a seal only when Florida law or the building department requires one.
Florida Statutes Chapter 471FBC-B 107.3.5 - #05Engineer of record seal, when engineeredDocumentation
When a Florida engineer prepared the structural drawings, the document carries that engineer's seal and signature. Contractor- or owner-prepared structural drawings need a seal only when Florida law or the building department requires one.
Florida Statutes Chapter 471FBC-B 107.3.5
ElectricalRequired
- #01AFCI and GFCI protectionLife Safety
AFCI protection for dwelling unit branch circuits per NEC 210.12; GFCI per NEC 210.8 at required locations.
NEC 210.8NEC 210.12 - #02Service size and load calculationCode
Electrical service and feeder sizing supported by NEC Article 220 load calculation.
NEC 220NEC 230
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your own inspection list comes from your approved plans. Inspections marked “If in scope” apply only when your plans include that work. Call (772) 222-6679 with questions.
Plumbing
Plumbing Underground
If in scope- Pipe material and sizingCritical
Compare underground drainage, sewer and water-service materials and sizes with the approved plans.
FBC-P 702.2FBC-P 702.3FBC-P 605.3FBC-P 603.1 - Trench bedding and coverCritical
Show trench bedding, pipe support and planned cover against the approved plans before backfill.
FBC-P 306.1FBC-P 306.2 - Pipe slope and supportCritical
Verify proper slope on drain lines and adequate support
FBC-P 704.1 - Cleanout locations
Verify cleanout access points are installed per plans
FBC-P 708.1 - Pressure testCritical
Show the required test for the installed drainage or water-supply section, with the measured result visible.
FBC-P 312.2FBC-P 312.5 - Trench left openCritical
Keep underground drain and water piping visible until inspection.
Electrical
Electrical Underground
If in scope- Conduit installationCritical
Verify conduit material, size, and routing per plans
NEC 300.5 - Burial depthCritical
Verify conduit burial depth meets code minimum
NEC 300.5 - UFER ground connectionCritical
Verify UFER grounding electrode is properly connected to rebar in footing
NEC 250.52 - Conduit protection
Verify conduit is protected from damage where exposed
NEC 300.5
Building
Footing / Grade Beam
- Footing dimensionsCritical
Verify footing width and depth match approved plans
- Rebar size and spacingCritical
Verify rebar size, spacing, and placement per plans
- UFER grounding electrodeCritical
Where the approved electrical design uses a concrete-encased electrode, show the specified material, length, placement, and connection before concrete.
NEC 250.52 - Foundation anchorage layout
Verify anchor bolt placement for sill plate attachment
Slab
If in scope- Slab vapor barrierCritical
Verify vapor barrier is installed under slab per plans
- Slab thickness and wire meshCritical
Verify slab thickness and reinforcement per plans
- Slab forms and elevationCritical
Verify slab outline, thickness, and elevations match the approved plans.
- Under-slab preparationCritical
Show prepared base, penetrations, and required under-slab work before the pour.
- Reinforcing supportCritical
Show slab steel or mesh supported at the planned position and with required laps.
Fill Cell / Column
If in scope- Pre-grout cell inspectionCritical
Show open reinforced cells and planned grout placement before concealment.
- Vertical rebar placementCritical
Verify vertical rebar is properly placed and spaced in block wall
- Open vertical cellsCritical
Keep reinforced masonry cells visible before grout is placed.
- Column reinforcementCritical
Verify column or pilaster steel, ties, laps, and cover against the plans.
- Cell cleanlinessCritical
Confirm reinforced cells are clear of mortar droppings and debris.
Lintel / Tie Beam
If in scope- Tie beam reinforcementCritical
Verify tie beam rebar size, spacing, and lap splices per plans
- Lintel reinforcementCritical
Verify lintel rebar and sizing over openings per plans
Window / Door Framing
If in scope- Anchor and fastener patternCritical
Verify anchoring method and fastener spacing per manufacturer installation instructions
- Rough opening dimensionsCritical
Measure each opening against the approved plans and selected unit.
- Buck attachmentCritical
Show buck material, anchors, spacing, and substrate before the unit covers them.
- Product approval matchCritical
Have the approved opening product and installation details available.
- Opening conditionCritical
Show a sound, prepared opening and required clearance for the unit.
Framing
- Wall stud spacing and sizeCritical
Verify stud size and spacing match approved plans
- Headers and beamsCritical
Verify header and beam sizes over openings per plans
- Top and bottom plate connectionsCritical
Verify double top plates with proper lapping and anchored bottom plates
- Corner and intersection bracingCritical
Verify proper bracing at corners and wall intersections
- Window and door rough openingsCritical
Verify rough openings match approved plans for size and location
- Hurricane straps and hold-downsCritical
Verify hurricane straps and hold-down hardware installed per plans
- Fire blocking
Verify fire blocking is installed at required locations
- Truss spacing and alignmentCritical
Verify truss spacing and alignment match approved plans
- Truss-to-wall connectionCritical
Verify hurricane clips or straps at every truss-to-wall connection
- Truss bracingCritical
Verify lateral and diagonal bracing is installed per truss engineering
- Truss engineering on siteCritical
Verify the truss engineering package is available and matches installed trusses
- Gable end bracing
Verify gable end trusses are properly braced
Roof Sheathing
If in scope- Roof sheathing attachmentCritical
Verify roof deck nailing pattern and edge spacing per the approved nailing schedule.
- Roof sheathing material and thicknessCritical
Verify roof sheathing panel material, thickness, and span rating match the approved plans.
- Panel gap spacing at roof deck
Verify proper edge gap between roof sheathing panels per the panel manufacturer.
Wall Sheathing
If in scope- Wall sheathing attachmentCritical
Verify wall sheathing nailing pattern and edge spacing per the approved nailing schedule (shear wall zones often require tighter spacing).
- Wall sheathing material and thicknessCritical
Verify wall sheathing panel material, thickness, and grade stamp match the approved plans.
- Panel gap spacing at walls
Verify proper edge gap between wall sheathing panels per the panel manufacturer.
Roof Dry-In
- Underlayment installationCritical
Verify roof underlayment is installed per code and manufacturer specs
Plumbing
Plumbing Rough-In
If in scope- Supply pipe sizing and materialCritical
Verify supply pipe sizes and material match approved plans
FBC-P 604.3FBC-P 605.4 - DWV pipe sizing and slopeCritical
Verify drain, waste, and vent pipe sizes and slope per plans
FBC-P 704.1 - Pipe support and hangingCritical
Verify pipes are properly supported at required intervals
FBC-P 308.1 - Vent termination locations
Show vent routing and approved termination through the roof or side wall before concealment.
FBC-P 903.1 - Water heater rough-in
Where a water heater is in scope, compare rough location and connections with approved plans and manufacturer instructions. Show a pan when tank leakage could cause damage.
FBC-P 502.1FBC-P 504.7 - Required rough testsCritical
Have the required water, drain, and vent tests ready before walls close.
FBC-P 312.1 - Shower and tub workCritical
Where shower or tub work is in scope, show pan/liner or tub installation and the required test before concealment.
Electrical
Electrical Rough-In
If in scope- Panel installationCritical
Verify electrical panel is properly mounted and sized per plans
- Wire sizing per circuitsCritical
Verify wire gauge matches breaker amperage for each circuit
NEC 240.4 - Box fill and installationCritical
Verify electrical boxes are properly installed and not overfilled
NEC 314.16 - GFCI and AFCI locationsCritical
Verify GFCI and AFCI protection is provided where required
NEC 210.8NEC 210.12 - Alarm installation methods where applicableCritical
Where the approved occupancy and scope require alarms, show the specified smoke-alarm power/interconnection method and any CO alarm installation; do not assume both are hardwired.
FBC-B 907.2.11 - Grounding and bondingCritical
Verify grounding electrode system and bonding connections
NEC 250.50
Mechanical
Mechanical Rough-In
If in scope- Ductwork installationCritical
Verify duct sizes, routing, and support match approved plans
FBC-M 603.1 - Duct sealingCritical
Verify duct joints and connections are properly sealed
FBC-M 603.9 - Refrigerant line installation
Where refrigerant lines are in scope, keep joints exposed before covering (FBC-M 1107.7). Compare sizing and insulation with approved plans and equipment instructions.
FBC-M 1107.7 - Equipment placementCritical
Verify air handler and condenser locations per plans with required clearances
FBC-M 304.1 - Return air pathway
Verify return air pathways are properly sized and located
FBC-M 601.6 - Concealed mechanical work visibleCritical
Leave duct, line, and exhaust routes accessible before walls close.
Building
Insulation
If in scope- Wall cavity insulation R-valueCritical
Verify wall insulation R-value matches energy calculations
FBC-E C402.2 - Ceiling/attic insulation R-valueCritical
Verify ceiling or attic insulation R-value per energy calculations
FBC-E C402.2 - Insulation coverage and gapsCritical
Verify no gaps, voids, or compression in insulation installation
FBC-E C402.2 - Air sealing
Verify air sealing at penetrations, top plates, and rim joists
FBC-E C402.5
Roof In-Progress
If in scope- Drip edge installationCritical
Verify drip edge is installed at eaves and rakes
- Valley and flashingCritical
Verify valley flashing and wall flashing are properly installed
- Roof penetration sealing
Verify all roof penetrations are properly sealed and flashed
- Covering materialCritical
Match roof tile, shingles, or metal panels to the approved plans and product approval.
- Covering attachmentCritical
Show fastener or clip pattern before it is concealed by the next course.
- Flashing installationCritical
Show flashing at valleys, walls, edges, and penetrations while accessible.
Exterior Wall Covering (Lath / Stucco / Siding)
If in scope- Wall covering material and installationCritical
Verify exterior wall covering material matches approved plans and is properly installed
- Weather-resistive barrierCritical
Verify weather-resistive barrier is properly installed behind cladding
- Flashing at penetrations and transitionsCritical
Verify flashing is installed at windows, doors, and wall transitions
- Fastener pattern and spacing
Verify cladding fastener type and spacing per manufacturer and plans
Drywall / Gypsum Board
If in scopeBD-DependentMost jurisdictions skip this inspection for this project type. Confirm with your building department whether they'll require it.
- Drywall thickness and typeCritical
Match board type, thickness, exposure rating, and layers to the approved rated or shear assembly.
- Fastener spacingCritical
Verify screw or nail spacing meets code requirements
- Fire-rated assembliesCritical
Verify fire-rated walls and ceilings have proper drywall layers per rating
Electrical
Electrical Final
If in scope- Panel complete and labeledCritical
Verify panel cover installed, all breakers labeled, no open knockouts
NEC 408.4NEC 408.7 - GFCI and AFCI operationalCritical
Verify all GFCI and AFCI devices test and reset properly
NEC 210.8NEC 210.12 - Receptacle and switch functionCritical
Verify outlets and switches operate correctly throughout
- Light fixtures installed
Verify all light fixtures are installed and operational
NEC 210.70 - Exterior lighting and outletsCritical
Where in scope, demonstrate outdoor GFCI protection and required exterior entrance lighting.
NEC 210.8NEC 210.70
Plumbing
Plumbing Final
If in scope- Fixture setting, connections and operationCritical
Show in-scope fixtures level and aligned, connected to required water and drainage systems, and operating without visible leaks.
FBC-P 405.3FBC-P 301.3FBC-P 301.4 - No visible leaksCritical
During the live fixture run, show exposed connections and surrounding areas with no visible leaks.
- Water heater installationCritical
Where a water heater is in scope, show the installed heater, relief valve and discharge piping; show a pan and drain where leakage could cause damage.
FBC-P 504.4FBC-P 504.6FBC-P 504.7 - Hose bibbs and exterior plumbing
Verify exterior hose bibbs have backflow prevention
FBC-P 608.16.4.2 - All fixtures connectedCritical
Confirm fixtures and water-using equipment are installed and connected.
Mechanical
Mechanical Final
If in scope- Installed mechanical system operationCritical
Demonstrate each mechanical system in the approved scope. Show heating and cooling modes only if the installed equipment provides them.
- Equipment labels and data plates
Verify equipment nameplates match approved plans for capacity and efficiency
FBC-M 304.1 - Installed mechanical equipmentCritical
Show equipment installed for this scope, with access and clearances against approved plans and manufacturer instructions.
FBC-M 304.1 - Condensate drainCritical
Where cooling equipment produces condensate, show the drain and approved termination.
FBC-M 307.2 - Duct registers and grilles
Where ducted supply or return air is in scope, show representative installed registers and grilles.
FBC-M 603.18 - Equipment operationCritical
Demonstrate system operation in heating, cooling, or exhaust mode as applicable.
Building
Roof Final
- Roofing material installationCritical
Verify roofing material is installed per manufacturer specs and approved plans
- Flashing completenessCritical
Verify all flashing is complete at walls, valleys, penetrations, and edges
- Ridge vent or ventilation
Show roof or attic ventilation where the approved design requires it.
- Covering attachment evidenceCritical
Show in-progress evidence for concealed fasteners, clips or adhesive and visible attachment at roof edges and terminations.
- Cleanup and debris removal
Verify job site is clean with no exposed nails or debris in gutters
- Completed roofCritical
Confirm all roof planes, edges, penetrations, and terminations are complete.
Building Final
Typical Final- Garage structure completeCritical
Confirm framing, roof, openings, and anchorage match approved plans.
FBC-B 110.3 - Vehicle door and safe accessCritical
Demonstrate garage door operation, safety features, and person door where shown.