Commercial

Commercial Generator Install

Fixed standby generator and transfer equipment at commercial, apartment, or condo property. Add gas inspections when a new gas line is included.

Last updated: Sep 29, 2026

Section 1

Required Documents

Submit these with your initial project package.

Always required

  • Construction Plans
    Plans showing generator installation, electrical connections, and fuel supply. Plans prepared by a Florida-registered architect or engineer carry that professional's seal. Plans prepared by a contractor or owner are accepted without a seal unless Florida law or the building department requires professional plans.
  • Equipment Specifications
    Manufacturer specifications for the generator including capacity, fuel type, and output rating
  • Electrical Load Calculations
    Electrical load calculations showing generator capacity relative to the loads it will serve
  • Site Plan
    Site plan showing generator placement, clearances, and fuel supply routing

Courtesy screen

Courtesy screen on every plan review

Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.

  1. #01Plan and document coordination

    Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.

    FBC-B 107.2.1
  2. #02Zoning and site coordination

    Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.

  3. #03Floodplain coordination

    Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.

  4. #04Fire-authority coordination

    Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.

Section 2

Approval criteria for this project type

These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.

ElectricalConditional review scope

Conditional review scopePlan review is not required for this scope under FBC 107.3.5. FCC reviews these items only when the building department specifically requires it, or the client opts in.
  1. #01Generator disconnect, transfer switch, and labelingLife Safety

    Standby generator installation requires approved transfer switch, disconnect, and required labeling per NEC 702 / 445.

    NEC 445NEC 702NEC 230.82
  2. #02Grounding and bondingLife Safety

    Grounding electrode, equipment grounding, and bonding per NEC Article 250.

    NEC 250
  3. #03Plan review applicability (FBC 107.3.5 minimum criteria)Documentation

    Commercial standby/emergency systems fall under NEC 700/701/702 compliance. FCC performs this review only when the building department requires plan review or the client opts in.

    FBC-B 107.3.5

Items marked Conditional review scope are non-blocking. Per FBC 107.3.5, plan review isn't required for these scopes — FCC reviews them when the building department requests it or the client wants the extra set of eyes.

Section 3

Inspection Walkthrough

Inspections are listed in their typical phase order. Your own inspection list comes from your approved plans. Inspections marked “If in scope” apply only when your plans include that work. Call (772) 222-6679 with questions.

Plumbing

Phase #1

Gas Rough Piping

If in scope
  1. Piping route and sizeCritical

    Match gas piping material, sizes, and route to approved plans.

  2. Supports and protectionCritical

    Show pipe supports, sleeves, and protection at penetrations.

  3. Valves and fittingsCritical

    Keep shutoffs, fittings, and concealed joints visible before covering.

  4. Required separationCritical

    Show separation from other utilities and ignition sources where plans require it.

  5. Rough test readinessCritical

    Have the required rough piping test setup ready for inspection.

    FBC-FG 406.1

Electrical

Phase #2

Electrical Rough-In

  1. Generator pad and placementCritical

    Verify generator is placed on approved pad with required clearances from structure, openings, and property lines

    FBC-M 304.1
  2. Electrical connection and transfer switchCritical

    Verify transfer switch installation, wire sizing, and connection to main panel per plans

    NEC 702.5NEC 445.13
  3. GroundingCritical

    Show approved grounding and bonding arrangement for this fixed generator and transfer configuration, including the building electrode system where used.

    NEC 250.50

Plumbing

Phase #3

Gas Final Piping (Pressure Test)

If in scope
  1. Pressure test setupCritical

    Show the pressure gauge, isolated piping, and required test setup.

    FBC-FG 406.4
  2. Test recordCritical

    Document test pressure and duration required by the authority having jurisdiction.

    FBC-FG 406.1
  3. Concealed work recordCritical

    Provide prior rough inspection record for piping now covered.

  4. Piping completenessCritical

    Confirm all piping, valves, and terminations are installed before appliance connection.

  5. Leak checkCritical

    Document any required leak check before gas is placed in service.

    FBC-FG 406.5

Electrical

Phase #4

Power Release / Service

If in scope
  1. Service equipment installedCritical

    Show meter enclosure, disconnect, and service conductors ready for utility connection.

  2. Service grounding and bondingCritical

    Show grounding electrode and bonding connections at the service.

  3. Panel and circuit identificationCritical

    Label service and affected panels clearly.

  4. Utility release readinessCritical

    Have the approved service plans and required utility coordination available.

  5. Safe energizationCritical

    Confirm exposed wiring is protected and all covers are installed before release.

Plumbing

Phase #5

Gas Final

If in scope
  1. Appliances connectedCritical

    Confirm each gas appliance and shutoff is installed and connected.

  2. Venting and combustion airCritical

    Show venting and combustion air provisions for applicable appliances.

  3. Pressure or leak testCritical

    Provide required final test results for new and affected existing piping.

    FBC-FG 406.5
  4. Equipment operationCritical

    Demonstrate safe operation and ignition of each installed appliance.

  5. Labels and accessCritical

    Keep appliance labels, shutoffs, and service access visible.

Electrical

Phase #6

Electrical Final

Typical Final
  1. Generator operational testCritical

    Verify generator starts, runs, and transfers load properly

  2. Transfer switch operationCritical

    Verify automatic transfer switch engages and disengages properly

    NEC 702.5
  3. Labeling and signageCritical

    Verify all required labels at generator, transfer switch, and main panel

    NEC 702.7NEC 445.11
  4. Sound and vibration

    Verify generator meets any local noise ordinance requirements