- #01Plan and document coordination
Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.
FBC-B 107.2.1 - #02Zoning and site coordination
Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #03Floodplain coordination
Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #04Fire-authority coordination
Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
Commercial HVAC Changeout
Replacement of an existing commercial, apartment, or condo HVAC unit without new concealed ductwork.
Last updated: Sep 29, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- AHRI Certification SheetAHRI performance certification showing matched system ratings for the replacement HVAC equipment
- Construction PlansHVAC plans for the equipment change. Plans prepared by a Florida-registered architect or engineer carry that professional's seal. Plans prepared by a contractor or owner are accepted without a seal unless Florida law or the building department requires professional plans.
Conditional
- Survey / Site PlanSurvey or site plan showing new equipment locationWhenRequired if HVAC system is being relocated to a new location
Courtesy screen
Courtesy screen on every plan review
Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.
Section 2
Approval criteria for this project type
These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.
MechanicalConditional review scope
- #01Combustion air and ventingLife Safety
Fuel-fired equipment requires combustion air and proper venting per FBC-M 303 / 804.
FBC-M 303FBC-M 804FBC-FG 304.1FBC-FG 503 - #02HVAC changeout installation requirementsCode
Replacement HVAC installation must address refrigerant line set, condensate drain, electrical disconnect, and energy code compliance.
FBC-M 307FBC-M 1101FBC-E C403NEC 440 - #03Plan review applicability (FBC 107.3.5)Documentation
Per FBC-B 107.3.5, plan review is not required for replacing existing equipment (Exemption #1). FCC performs this review only when the building department requires plan review or the client opts in.
FBC-B 107.3.5
Items marked Conditional review scope are non-blocking. Per FBC 107.3.5, plan review isn't required for these scopes — FCC reviews them when the building department requests it or the client wants the extra set of eyes.
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your own inspection list comes from your approved plans. Inspections marked “If in scope” apply only when your plans include that work. Call (772) 222-6679 with questions.
Mechanical
Mechanical Final
Typical Final- System operational testCritical
Demonstrate the installed system operating in its approved heating, cooling, exhaust, or hood mode as applicable.
- Equipment clearancesCritical
Verify air handler and condenser have required clearances for service
FBC-M 304.1 - Equipment labels and data plates
Match installed equipment model and rating to approved plans and manufacturer instructions.
FBC-M 304.1 - Thermostat operation
Verify thermostat controls heating and cooling modes properly