- #01Plan and document coordination
Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.
FBC-B 107.2.1 - #02Zoning and site coordination
Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #03Floodplain coordination
Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #04Fire-authority coordination
Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
Commercial Pool Construction
New commercial or multifamily pool or spa, including shell, bonding, equipment, deck when built, and required safety features.
Last updated: Oct 14, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Construction PlansPool construction plans. Plans prepared by a Florida-registered architect or engineer carry that professional's seal. Plans prepared by a contractor or owner are accepted without a seal unless Florida law or the building department requires professional plans.
- TDH CalculationsTurnover, Design, and Hydraulic (TDH) calculations for the pool system
- Site Plan / SurveySite plan or survey showing pool location, setbacks, and safety barrier locations
Conditional
- Equipment SpecificationsManufacturer specifications for pump, filter, heater, and other pool equipment (recommended, not required)WhenGuidance only: Not required. FCC recommends manufacturer cut sheets (pump, filter, heater, lights, drain covers) because some building departments ask for them. An engineer's equipment table on the plans is enough, and missing cut sheets are never a reason to reject the submission.
Courtesy screen
Courtesy screen on every plan review
Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.
Section 2
Plan Review Criteria for this project type
These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.
BuildingRequired
- #01Pool barrier (commercial)Life Safety
Commercial pool barrier per FBC-B 454.1.3.1.9 including fencing, gates, and alarms as applicable.
FBC-B 454.1.3.1.9 - #02Design wind speed & exposureLife Safety
Structural drawings must declare design wind speed (Vult) and exposure category matching the jurisdiction's wind speed map.
FBC-B 1609ASCE 7-22 - #03Accessibility scoping (FBC-A)Code
Alteration or new commercial work triggers accessibility requirements in altered areas and along path of travel.
FBC-A 202FBC-A 206FBC-A 202.4 - #04Engineer of record seal, when engineeredDocumentation
When a Florida engineer prepared the structural drawings, the document carries that engineer's seal and signature. Contractor- or owner-prepared structural drawings need a seal only when Florida law or the building department requires one.
Florida Statutes Chapter 471FBC-B 107.3.5
MechanicalRequired
- #01Specialty exhaust and make-up airLife Safety
Kitchen hoods, chemical storage, spray booths, and similar require specialty exhaust per FBC-M Ch. 5 with matched make-up air.
FBC-M 508.1FBC-M 502.7FBC-M 502.8FBC-M 506FBC-M 507 - #02Ventilation per FBC-M 403 (occupancy-based)Code
Outdoor air ventilation rates per FBC-M Table 403.3 based on occupancy classification and occupant load.
FBC-M 403ASHRAE 62.1
ElectricalRequired
- #01Equipotential bonding (commercial pool)Life Safety
Commercial pool equipotential bonding grid per NEC 680.26.
NEC 680.26 - #02GFCI / luminaires / disconnects (commercial pool)Life Safety
Pool circuits must include GFCI protection; underwater luminaires and motor disconnects per NEC 680.
NEC 680
PlumbingRequired
- #01Suction entrapment / VGBA (commercial pool)Life Safety
Commercial pool must comply with VGBA suction entrapment prevention.
VGBAFBC-B 454.1.6.5.10.2
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your own inspection list comes from your approved plans. Inspections marked “If in scope” apply only when your plans include that work. Call (772) 222-6679 with questions.
Building
Pool Steel / Bond / Pressure Test
- Shell steel to plansCritical
Show shell steel size, spacing, and coverage against the approved pool engineering before concrete or gunite.
FBC-B 110.3 - Main drain clear of steelCritical
Show the main drain set in place and not touching the steel.
FBC-B 110.3 - Shell bonding at four pointsCritical
Show the shell steel bonded at four points spaced around the pool, with the bonding conductor left to tie into the deck and equipment.
NEC 680.26 - Initial pressure testCritical
Show the pool piping installed so far holding its test pressure.
FBC-B 110.3
Plumbing
Plumbing Underground
- Open ditch to the equipment padCritical
Show the pool piping in the open trench all the way from the pool to where the equipment will be set, before backfill.
FBC-B 110.3 - Burial depthCritical
Measure pipe cover against the approved plans before backfill.
FBC-B 110.3 - Pressure testCritical
Show the underground pool piping holding its test pressure.
FBC-B 110.3 - Pipe sizing per plans
Verify pipe sizes match the approved plans.
FBC-B 110.3
Electrical
Electrical Underground
- Open ditch to the equipment padCritical
Show the conduit in the open trench all the way to where the equipment will be set, before backfill.
NEC 680.11 - Burial depth verificationCritical
Verify conduit burial depth meets minimum code requirements.
NEC 680.11 - Pool-area underground wiring methodCritical
Check wiring method and routing near or under the pool against approved plans and NEC 680.11; do not impose a blanket five-foot setback.
NEC 680.11 - Bonding connections at undergroundCritical
Show pool equipotential-bonding parts that will be buried; verify other underground equipment grounding separately.
NEC 680.26NEC 680.6 - Equipment grounding at underground boxesCritical
Where conductors splice or terminate in an underground box, show equipment-grounding conductor continuity and connections before backfill.
NEC 250.148
Building
Footing / Grade Beam
If in scope- Separate structural footing onlyCritical
Use this inspection only if the approved pool plans include a separate structural footing or grade beam.
- Footing forms and steelCritical
Show the footing location, forms, dimensions, and reinforcing before the pour.
- Footing bondCritical
Show the footing steel bonded to the pool bonding where the plans call for it.
NEC 680.26 - Plan matchCritical
Confirm the separate footing matches the approved structural detail.
Pool Deck / Bond
- Deck bond tied to the shell bondCritical
Show the bonding from the steel inspection tied into the deck grid or approved perimeter bond before the pour; a separate wire is not universal.
NEC 680.26 - Footing bond, if a footingCritical
If the plans show a footing, show the pool bonding tied into the footing steel.
NEC 680.26 - Deck reinforcement layoutCritical
Verify deck rebar spacing, overlap, and placement per plans.
- Plumbing and electrical conduit in place
Verify plumbing lines and electrical conduit are installed before the pour.
- Deck drainageCritical
Measure deck slope and show drainage away from the pool or toward approved deck drains.
ISPSC 306.5ISPSC 306.5.1
Plumbing
Gas Rough Piping
If in scope- Piping route and sizeCritical
Match gas piping material, sizes, and route to approved plans.
- Supports and protectionCritical
Show pipe supports, sleeves, and protection at penetrations.
- Valves and fittingsCritical
Keep shutoffs, fittings, and concealed joints visible before covering.
- Required separationCritical
Show separation from other utilities and ignition sources where plans require it.
- Rough test readinessCritical
Have the required rough piping test setup ready for inspection.
FBC-FG 406.1
Electrical
Electrical Final
- Barrier in place before fillCritical
This is the pre-fill inspection. Before water goes in, show the barrier, gates, and any required alarms or approved safety cover are complete.
FBC-B 454.2.17ISPSC 305.3 - Pool light installationCritical
Verify pool lights are properly installed per plans and NEC.
NEC 680.23 - Equipotential bonding completeCritical
Compare required metallic parts and connections with the approved pool bonding plan; do not impose a blanket five-foot rule.
NEC 680.26 - GFCI protection operationalCritical
Demonstrate required GFCI devices for the pool motor and pool-area receptacles operate.
NEC 680.21NEC 680.22 - Grounding connectionsCritical
Verify pool electrical equipment grounding separately from equipotential bonding.
NEC 680.6 - Disconnect switchCritical
Show the approved disconnecting means and accessible location against the equipment plans.
FBC-B 110.3
Building
Pool Pre-fill Safety Barrier/Electrical Final
- Barrier perimeterCritical
Show the complete barrier before water is added.
- Gates self-close and latchCritical
Demonstrate each gate closing and latching.
- Door and window alarmsCritical
Demonstrate the required alarms and safety features.
- Pool electrical finalCritical
Show completed pool electrical work and bonding against the approved plans and NEC 680.
NEC 680
Plumbing
Gas Final
If in scope- Appliances connectedCritical
Confirm each gas appliance and shutoff is installed and connected.
- Venting and combustion airCritical
Show venting and combustion air provisions for applicable appliances.
- Pressure or leak testCritical
Provide required final test results for new and affected existing piping.
FBC-FG 406.5 - Equipment operationCritical
Demonstrate safe operation and ignition of each installed appliance.
- Labels and accessCritical
Keep appliance labels, shutoffs, and service access visible.
Building
Pool Final
Typical Final- Completed poolCritical
Show the finished pool and equipment against the approved plans.
FBC-B 110.3 - Equipment runningCritical
Demonstrate pump, filter, and any heater operating against the approved equipment schedule, with no leaks.
FBC-B 110.3 - Barrier and gates confirmedCritical
Confirm the barrier checked at pre-fill is still complete and gates self-close and self-latch.
FBC-B 454.2.17ISPSC 305.3 - Safety devicesCritical
Demonstrate approved alarms or other required safety devices.
FBC-B 454.2.17 - Suction outletsCritical
Show installed covers and suction system identification.
ISPSC 311.1ISPSC 312.4.4 - Backflow preventionCritical
Show required backflow protection on the pool fill line.
FBC-B 110.3 - Final plan matchCritical
Compare finished pool, deck, barrier, and access with the approved plan.
FBC-B 110.3
