Commercial

Commercial Pool Construction

New commercial or multifamily pool or spa, including shell, bonding, equipment, deck when built, and required safety features.

Last updated: Oct 14, 2026

Section 1

Required Documents

Submit these with your initial project package.

Always required

  • Construction Plans
    Pool construction plans. Plans prepared by a Florida-registered architect or engineer carry that professional's seal. Plans prepared by a contractor or owner are accepted without a seal unless Florida law or the building department requires professional plans.
  • TDH Calculations
    Turnover, Design, and Hydraulic (TDH) calculations for the pool system
  • Site Plan / Survey
    Site plan or survey showing pool location, setbacks, and safety barrier locations

Conditional

  • Equipment Specifications
    Manufacturer specifications for pump, filter, heater, and other pool equipment (recommended, not required)
    WhenGuidance only: Not required. FCC recommends manufacturer cut sheets (pump, filter, heater, lights, drain covers) because some building departments ask for them. An engineer's equipment table on the plans is enough, and missing cut sheets are never a reason to reject the submission.

Courtesy screen

Courtesy screen on every plan review

Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.

  1. #01Plan and document coordination

    Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.

    FBC-B 107.2.1
  2. #02Zoning and site coordination

    Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.

  3. #03Floodplain coordination

    Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.

  4. #04Fire-authority coordination

    Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.

Section 2

Plan Review Criteria for this project type

These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.

BuildingRequired

  1. #01Pool barrier (commercial)Life Safety

    Commercial pool barrier per FBC-B 454.1.3.1.9 including fencing, gates, and alarms as applicable.

    FBC-B 454.1.3.1.9
  2. #02Design wind speed & exposureLife Safety

    Structural drawings must declare design wind speed (Vult) and exposure category matching the jurisdiction's wind speed map.

    FBC-B 1609ASCE 7-22
  3. #03Accessibility scoping (FBC-A)Code

    Alteration or new commercial work triggers accessibility requirements in altered areas and along path of travel.

    FBC-A 202FBC-A 206FBC-A 202.4
  4. #04Engineer of record seal, when engineeredDocumentation

    When a Florida engineer prepared the structural drawings, the document carries that engineer's seal and signature. Contractor- or owner-prepared structural drawings need a seal only when Florida law or the building department requires one.

    Florida Statutes Chapter 471FBC-B 107.3.5

MechanicalRequired

  1. #01Specialty exhaust and make-up airLife Safety

    Kitchen hoods, chemical storage, spray booths, and similar require specialty exhaust per FBC-M Ch. 5 with matched make-up air.

    FBC-M 508.1FBC-M 502.7FBC-M 502.8FBC-M 506FBC-M 507
  2. #02Ventilation per FBC-M 403 (occupancy-based)Code

    Outdoor air ventilation rates per FBC-M Table 403.3 based on occupancy classification and occupant load.

    FBC-M 403ASHRAE 62.1

ElectricalRequired

  1. #01Equipotential bonding (commercial pool)Life Safety

    Commercial pool equipotential bonding grid per NEC 680.26.

    NEC 680.26
  2. #02GFCI / luminaires / disconnects (commercial pool)Life Safety

    Pool circuits must include GFCI protection; underwater luminaires and motor disconnects per NEC 680.

    NEC 680

PlumbingRequired

  1. #01Suction entrapment / VGBA (commercial pool)Life Safety

    Commercial pool must comply with VGBA suction entrapment prevention.

    VGBAFBC-B 454.1.6.5.10.2

Section 3

Inspection Walkthrough

Inspections are listed in their typical phase order. Your own inspection list comes from your approved plans. Inspections marked “If in scope” apply only when your plans include that work. Call (772) 222-6679 with questions.

Building

Phase #1

Pool Steel / Bond / Pressure Test

  1. Shell steel to plansCritical

    Show shell steel size, spacing, and coverage against the approved pool engineering before concrete or gunite.

    FBC-B 110.3
  2. Main drain clear of steelCritical

    Show the main drain set in place and not touching the steel.

    FBC-B 110.3
  3. Shell bonding at four pointsCritical

    Show the shell steel bonded at four points spaced around the pool, with the bonding conductor left to tie into the deck and equipment.

    NEC 680.26
  4. Initial pressure testCritical

    Show the pool piping installed so far holding its test pressure.

    FBC-B 110.3

Plumbing

Phase #2

Plumbing Underground

  1. Open ditch to the equipment padCritical

    Show the pool piping in the open trench all the way from the pool to where the equipment will be set, before backfill.

    FBC-B 110.3
  2. Burial depthCritical

    Measure pipe cover against the approved plans before backfill.

    FBC-B 110.3
  3. Pressure testCritical

    Show the underground pool piping holding its test pressure.

    FBC-B 110.3
  4. Pipe sizing per plans

    Verify pipe sizes match the approved plans.

    FBC-B 110.3

Electrical

Phase #3

Electrical Underground

  1. Open ditch to the equipment padCritical

    Show the conduit in the open trench all the way to where the equipment will be set, before backfill.

    NEC 680.11
  2. Burial depth verificationCritical

    Verify conduit burial depth meets minimum code requirements.

    NEC 680.11
  3. Pool-area underground wiring methodCritical

    Check wiring method and routing near or under the pool against approved plans and NEC 680.11; do not impose a blanket five-foot setback.

    NEC 680.11
  4. Bonding connections at undergroundCritical

    Show pool equipotential-bonding parts that will be buried; verify other underground equipment grounding separately.

    NEC 680.26NEC 680.6
  5. Equipment grounding at underground boxesCritical

    Where conductors splice or terminate in an underground box, show equipment-grounding conductor continuity and connections before backfill.

    NEC 250.148

Building

Phase #4

Footing / Grade Beam

If in scope
  1. Separate structural footing onlyCritical

    Use this inspection only if the approved pool plans include a separate structural footing or grade beam.

  2. Footing forms and steelCritical

    Show the footing location, forms, dimensions, and reinforcing before the pour.

  3. Footing bondCritical

    Show the footing steel bonded to the pool bonding where the plans call for it.

    NEC 680.26
  4. Plan matchCritical

    Confirm the separate footing matches the approved structural detail.

Phase #5

Pool Deck / Bond

  1. Deck bond tied to the shell bondCritical

    Show the bonding from the steel inspection tied into the deck grid or approved perimeter bond before the pour; a separate wire is not universal.

    NEC 680.26
  2. Footing bond, if a footingCritical

    If the plans show a footing, show the pool bonding tied into the footing steel.

    NEC 680.26
  3. Deck reinforcement layoutCritical

    Verify deck rebar spacing, overlap, and placement per plans.

  4. Plumbing and electrical conduit in place

    Verify plumbing lines and electrical conduit are installed before the pour.

  5. Deck drainageCritical

    Measure deck slope and show drainage away from the pool or toward approved deck drains.

    ISPSC 306.5ISPSC 306.5.1

Plumbing

Phase #6

Gas Rough Piping

If in scope
  1. Piping route and sizeCritical

    Match gas piping material, sizes, and route to approved plans.

  2. Supports and protectionCritical

    Show pipe supports, sleeves, and protection at penetrations.

  3. Valves and fittingsCritical

    Keep shutoffs, fittings, and concealed joints visible before covering.

  4. Required separationCritical

    Show separation from other utilities and ignition sources where plans require it.

  5. Rough test readinessCritical

    Have the required rough piping test setup ready for inspection.

    FBC-FG 406.1

Electrical

Phase #7

Electrical Final

  1. Barrier in place before fillCritical

    This is the pre-fill inspection. Before water goes in, show the barrier, gates, and any required alarms or approved safety cover are complete.

    FBC-B 454.2.17ISPSC 305.3
  2. Pool light installationCritical

    Verify pool lights are properly installed per plans and NEC.

    NEC 680.23
  3. Equipotential bonding completeCritical

    Compare required metallic parts and connections with the approved pool bonding plan; do not impose a blanket five-foot rule.

    NEC 680.26
  4. GFCI protection operationalCritical

    Demonstrate required GFCI devices for the pool motor and pool-area receptacles operate.

    NEC 680.21NEC 680.22
  5. Grounding connectionsCritical

    Verify pool electrical equipment grounding separately from equipotential bonding.

    NEC 680.6
  6. Disconnect switchCritical

    Show the approved disconnecting means and accessible location against the equipment plans.

    FBC-B 110.3

Building

Phase #8

Pool Pre-fill Safety Barrier/Electrical Final

  1. Barrier perimeterCritical

    Show the complete barrier before water is added.

  2. Gates self-close and latchCritical

    Demonstrate each gate closing and latching.

  3. Door and window alarmsCritical

    Demonstrate the required alarms and safety features.

  4. Pool electrical finalCritical

    Show completed pool electrical work and bonding against the approved plans and NEC 680.

    NEC 680

Plumbing

Phase #9

Gas Final

If in scope
  1. Appliances connectedCritical

    Confirm each gas appliance and shutoff is installed and connected.

  2. Venting and combustion airCritical

    Show venting and combustion air provisions for applicable appliances.

  3. Pressure or leak testCritical

    Provide required final test results for new and affected existing piping.

    FBC-FG 406.5
  4. Equipment operationCritical

    Demonstrate safe operation and ignition of each installed appliance.

  5. Labels and accessCritical

    Keep appliance labels, shutoffs, and service access visible.

Building

Phase #10

Pool Final

Typical Final
  1. Completed poolCritical

    Show the finished pool and equipment against the approved plans.

    FBC-B 110.3
  2. Equipment runningCritical

    Demonstrate pump, filter, and any heater operating against the approved equipment schedule, with no leaks.

    FBC-B 110.3
  3. Barrier and gates confirmedCritical

    Confirm the barrier checked at pre-fill is still complete and gates self-close and self-latch.

    FBC-B 454.2.17ISPSC 305.3
  4. Safety devicesCritical

    Demonstrate approved alarms or other required safety devices.

    FBC-B 454.2.17
  5. Suction outletsCritical

    Show installed covers and suction system identification.

    ISPSC 311.1ISPSC 312.4.4
  6. Backflow preventionCritical

    Show required backflow protection on the pool fill line.

    FBC-B 110.3
  7. Final plan matchCritical

    Compare finished pool, deck, barrier, and access with the approved plan.

    FBC-B 110.3