Multi Family

New Condo

New condominium building with individually owned units. Use Multi Family Addition for added area on an existing building.

Last updated: Sep 29, 2026

Section 1

Required Documents

Submit these with your initial project package.

Always required

  • Construction Plans
    Construction plans for the building. Plans prepared by a Florida-registered architect or engineer carry that professional's seal. Plans prepared by a contractor or owner are accepted without a seal unless Florida law or the building department requires professional plans.
  • Energy Compliance Forms
    Energy compliance documentation per FBC Chapter 13 / IECC
  • Product Approvals
    Florida Product Approvals for windows, doors, roofing materials, and other regulated components
  • Site Plan / Survey
    Current site plan or survey showing property boundaries, setbacks, and building footprint

Conditional

  • Truss Engineering OR Truss Deferral Affidavit
    Truss engineering package, conventional framing per FBC, or a truss deferral letter requesting deferred submittal of truss engineering.
    WhenRequired only when structure uses pre-engineered trusses and truss engineering is not shown in the plan set; satisfied by truss engineering in plan set OR conventional framing per FBC OR a truss deferral letter.

Courtesy screen

Courtesy screen on every plan review

Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.

  1. #01Plan and document coordination

    Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.

    FBC-B 107.2.1
  2. #02Zoning and site coordination

    Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.

  3. #03Floodplain coordination

    Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.

  4. #04Fire-authority coordination

    Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.

Section 2

Approval criteria for this project type

These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.

BuildingRequired

  1. #01Design wind speed & exposureLife Safety

    Structural drawings must declare design wind speed (Vult) and exposure category matching the jurisdiction's wind speed map.

    FBC-B 1609ASCE 7-22
  2. #02Egress from sleeping roomsLife Safety

    Where FBC-B 1030.1 requires emergency escape and rescue openings (Group R-2 per Tables 1006.3.3(1) and 1006.3.3(2); sleeping rooms below the fourth story), each sleeping room must have one meeting FBC-B 1030 dimensions.

    FBC-B 1030
  3. #03Smoke and CO alarm coverageLife Safety

    Smoke alarms in each sleeping room, outside each sleeping area, and on each story. CO alarms where fuel-fired appliances or attached garages exist.

    FBC-B 907.2.11FBC-B 915.1
  4. #04Structural wall section and load pathLife Safety

    A continuous wall section from foundation through roof must show framing, sheathing, connectors, and uplift resistance.

    FBC-B 1603FBC-B 1604.8
  5. #05Fire-rated unit separationLife Safety

    Dwelling-unit and corridor separations must maintain the original fire-resistance rating through any new work.

    FBC-B 420FBC-B 711FBC-B 708
  6. #06Florida product approvalCode

    Florida product approval (statewide FL#, Miami-Dade NOA, or local approval under F.S. 553.8425) must be listed for each product subject to Florida product approval (F.S. 553.842 and 553.8425; Rule 61G20-3 F.A.C.).

    F.S. 553.842F.S. 553.8425Rule 61G20-3 F.A.C.FBC-B 1709.5FBC-B 1709.9FBC-B 1609.1.2FBC-B 1504

MechanicalRequired

  1. #01Combustion air and ventingLife Safety

    Fuel-fired equipment requires combustion air and proper venting per FBC-M 303 / 804.

    FBC-M 303FBC-M 804FBC-FG 304.1FBC-FG 503
  2. #02Manual J / S / D load calculationPerformance

    HVAC equipment sizing must rest on a heating and cooling load calculation per FBC-M 312.1 (ASHRAE/ACCA Standard 183 or an approved equivalent procedure, such as ACCA Manual J); ducts sized per FBC-M 603.2: ducts wholly within a single dwelling unit by ACCA Manual D, the appliance manufacturer's instructions or another approved method; all other ducts (shared, or serving more than one unit) by the ASHRAE Handbook of Fundamentals or an equivalent computation procedure.

    FBC-M 312.1FBC-M 603.2
  3. #03VentilationPerformance

    Whole-house or occupancy-based ventilation per FBC-M 403.

    FBC-M 403

ElectricalRequired

  1. #01AFCI and GFCI protectionLife Safety

    AFCI protection for dwelling unit branch circuits per NEC 210.12; GFCI per NEC 210.8 at required locations.

    NEC 210.8NEC 210.12
  2. #02Grounding and bondingLife Safety

    Grounding electrode, equipment grounding, and bonding per NEC Article 250.

    NEC 250
  3. #03Service size and load calculationCode

    Electrical service and feeder sizing supported by NEC Article 220 load calculation.

    NEC 220NEC 230

PlumbingRequired

  1. #01Water service and DWV sizingCode

    Water service line sizing and DWV sizing consistent with fixture unit count.

    FBC-P 604FBC-P 709FBC-P 906
  2. #02Backflow preventionCode

    Backflow prevention required at well, irrigation, or other cross-connections per FBC-P 608.

    FBC-P 608

Section 3

Inspection Walkthrough

Inspections are listed in their typical phase order. Your own inspection list comes from your approved plans. Inspections marked “If in scope” apply only when your plans include that work. Call (772) 222-6679 with questions.

Plumbing

Phase #1

Plumbing Underground

  1. Pipe material and sizingCritical

    Verify pipe material and sizes match approved plans

    FBC-P 604.3FBC-P 605.4
  2. Burial depthCritical

    Show actual trench cover against approved plans and applicable pipe material; no universal plumbing burial depth is asserted.

  3. Pipe slope and supportCritical

    Verify proper slope on drain lines and adequate support

    FBC-P 704.1FBC-P 306.1
  4. Pressure testCritical

    Verify plumbing system holds required pressure test

    FBC-P 312.2FBC-P 312.5
  5. Cleanout locations

    Verify cleanout access points are installed per plans

    FBC-P 708.1

Electrical

Phase #2

Electrical Underground

If in scope
  1. Conduit installationCritical

    Verify conduit material, size, and routing per plans

    NEC 300.5
  2. Burial depthCritical

    Verify conduit burial depth meets code minimum

    NEC 300.5
  3. UFER ground connectionCritical

    Verify UFER grounding electrode is properly connected to rebar in footing

    NEC 250.52
  4. Conduit protection

    Verify conduit is protected from damage where exposed

    NEC 300.5

Mechanical

Phase #3

Mechanical Underground

If in scope
  1. Under-slab layoutCritical

    Match duct, refrigerant, or condensate line locations to approved plans.

  2. Material and protectionCritical

    Show listed materials, sleeves, and protection where lines pass through concrete or soil.

  3. Slope and drainageCritical

    Verify condensate drainage and slopes shown on the plans.

  4. Connections and supportsCritical

    Keep underground joints, supports, and transitions visible before backfill.

  5. Required testsCritical

    Have any specified duct or piping tests ready before concealment.

Building

Phase #4

Footing / Grade Beam

  1. Footing dimensionsCritical

    Verify footing width and depth match approved plans

  2. Rebar size and spacingCritical

    Verify rebar size, spacing, and placement per plans

  3. UFER grounding electrodeCritical

    Where the approved electrical design uses a concrete-encased electrode, show the specified material, length, placement, and connection before concrete.

    NEC 250.52
  4. Foundation anchorage layout

    Verify anchor bolt placement for sill plate attachment

Phase #5

Stem Wall

If in scope
  1. Stem wall layoutCritical

    Match the wall location and dimensions to the approved foundation plan.

  2. Wall reinforcementCritical

    Check vertical and horizontal reinforcement, laps, and clear cover before fill.

  3. Anchorage and connectionsCritical

    Show anchors and connections between the stem wall, footing, and floor system.

  4. Open cells and formsCritical

    Keep masonry cells or forms open and visible until inspection.

  5. Backfill holdCritical

    Do not backfill or conceal the stem wall before the inspection.

Phase #6

Piling / Pile Cap

If in scope
  1. Pile layoutCritical

    Match pile or pier locations and count to the approved structural plan.

  2. Pile size and depthCritical

    Document pile dimensions, embedment, or installation records required by the plans.

  3. Pile cap reinforcementCritical

    Show cap or pier forms, steel, laps, and cover before concrete.

  4. Connection to structureCritical

    Show specified pile-to-cap and cap-to-structure connections.

  5. Engineering documentationCritical

    Have the approved pile design and required installation or test records available.

Phase #7

Slab

If in scope
  1. Slab vapor barrierCritical

    Verify vapor barrier is installed under slab per plans

  2. Slab thickness and wire meshCritical

    Verify slab thickness and reinforcement per plans

  3. Slab forms and elevationCritical

    Verify slab outline, thickness, and elevations match the approved plans.

  4. Under-slab preparationCritical

    Show prepared base, penetrations, and required under-slab work before the pour.

  5. Reinforcing supportCritical

    Show slab steel or mesh supported at the planned position and with required laps.

Phase #8

Fill Cell / Column

If in scope
  1. Pre-grout cell inspectionCritical

    Show open reinforced cells and planned grout placement before concealment.

  2. Vertical rebar placementCritical

    Verify vertical rebar is properly placed and spaced in block wall

  3. Open vertical cellsCritical

    Keep reinforced masonry cells visible before grout is placed.

  4. Column reinforcementCritical

    Verify column or pilaster steel, ties, laps, and cover against the plans.

  5. Cell cleanlinessCritical

    Confirm reinforced cells are clear of mortar droppings and debris.

Phase #9

Lintel / Tie Beam

If in scope
  1. Tie beam reinforcementCritical

    Verify tie beam rebar size, spacing, and lap splices per plans

  2. Lintel reinforcementCritical

    Verify lintel rebar and sizing over openings per plans

Phase #10

Window / Door Framing

  1. Anchor and fastener patternCritical

    Verify anchoring method and fastener spacing per manufacturer installation instructions

  2. Rough opening dimensionsCritical

    Measure each opening against the approved plans and selected unit.

  3. Buck attachmentCritical

    Show buck material, anchors, spacing, and substrate before the unit covers them.

  4. Product approval matchCritical

    Have the approved opening product and installation details available.

  5. Opening conditionCritical

    Show a sound, prepared opening and required clearance for the unit.

Phase #11

Framing

  1. Wall stud spacing and sizeCritical

    Verify stud size and spacing match approved plans

  2. Headers and beamsCritical

    Verify header and beam sizes over openings per plans

  3. Top and bottom plate connectionsCritical

    Verify double top plates with proper lapping and anchored bottom plates

  4. Corner and intersection bracingCritical

    Verify proper bracing at corners and wall intersections

  5. Window and door rough openingsCritical

    Verify rough openings match approved plans for size and location

  6. Hurricane straps and hold-downsCritical

    Verify hurricane straps and hold-down hardware installed per plans

  7. Fire blocking

    Verify fire blocking is installed at required locations

  8. Fire separation wall framingCritical

    Verify party/fire wall is framed continuously from foundation to underside of roof sheathing per plans

  9. Draft stopping in party wallCritical

    Verify draft stopping is installed in concealed spaces of the fire separation wall

  10. Truss spacing and alignmentCritical

    Verify truss spacing and alignment match approved plans

  11. Truss-to-wall connectionCritical

    Verify hurricane clips or straps at every truss-to-wall connection

  12. Truss bracingCritical

    Verify lateral and diagonal bracing is installed per truss engineering

  13. Truss engineering on siteCritical

    Verify the truss engineering package is available and matches installed trusses

  14. Gable end bracing

    Verify gable end trusses are properly braced

Phase #12

Roof Sheathing

If in scope
  1. Roof sheathing attachmentCritical

    Verify roof deck nailing pattern and edge spacing per the approved nailing schedule.

  2. Roof sheathing material and thicknessCritical

    Verify roof sheathing panel material, thickness, and span rating match the approved plans.

  3. Panel gap spacing at roof deck

    Verify proper edge gap between roof sheathing panels per the panel manufacturer.

Phase #13

Wall Sheathing

If in scope
  1. Wall sheathing attachmentCritical

    Verify wall sheathing nailing pattern and edge spacing per the approved nailing schedule (shear wall zones often require tighter spacing).

  2. Wall sheathing material and thicknessCritical

    Verify wall sheathing panel material, thickness, and grade stamp match the approved plans.

  3. Panel gap spacing at walls

    Verify proper edge gap between wall sheathing panels per the panel manufacturer.

Phase #14

Roof Dry-In

  1. Underlayment installationCritical

    Verify roof underlayment is installed per code and manufacturer specs

Plumbing

Phase #15

Plumbing Rough-In

  1. Supply pipe sizing and materialCritical

    Verify supply pipe sizes and material match approved plans

    FBC-P 604.3FBC-P 605.4
  2. DWV pipe sizing and slopeCritical

    Verify drain, waste, and vent pipe sizes and slope per plans

    FBC-P 704.1
  3. Pipe support and hangingCritical

    Verify pipes are properly supported at required intervals

    FBC-P 308.1
  4. Vent termination locations

    Verify vent route and planned termination through the roof or side wall as approved.

    FBC-P 903.1
  5. Water heater rough-in

    Where a water heater is in scope, compare rough location and connections with approved plans and manufacturer instructions; show a pan if leakage could cause damage.

    FBC-P 502.1FBC-P 504.7

Electrical

Phase #16

Electrical Rough-In

  1. Panel installationCritical

    Verify electrical panel is properly mounted and sized per plans

  2. Wire sizing per circuitsCritical

    Verify wire gauge matches breaker amperage for each circuit

    NEC 240.4
  3. Box fill and installationCritical

    Verify electrical boxes are properly installed and not overfilled

    NEC 314.16
  4. GFCI and AFCI locationsCritical

    Verify GFCI and AFCI protection is provided where required

    NEC 210.8NEC 210.12
  5. Alarm installation methods where applicableCritical

    Where the approved occupancy and scope require alarms, show the specified smoke-alarm power/interconnection method and any CO alarm installation; do not assume both are hardwired.

    FBC-B 907.2.11
  6. Grounding and bondingCritical

    Verify grounding electrode system and bonding connections

    NEC 250.50

Mechanical

Phase #17

Mechanical Rough-In

  1. Ductwork installationCritical

    Verify duct sizes, routing, and support match approved plans

    FBC-M 603.1
  2. Duct sealingCritical

    Verify duct joints and connections are properly sealed

    FBC-M 603.9
  3. Equipment placementCritical

    Verify air handler and condenser locations per plans with required clearances

    FBC-M 304.1
  4. Refrigerant line installation

    Match refrigerant line size, insulation, and route to approved plans; leave field-installed joints visible before cover.

    FBC-M 1107.7
  5. Return air pathway

    Show return-air path and grille or transfer opening against approved mechanical plans.

    FBC-M 601.6

Building

Phase #18

Fire / Smoke Penetrations

If in scope
  1. Rated assembly identificationCritical

    Identify each rated wall, floor, smoke barrier, or partition shown on the plans.

  2. Listed system matchCritical

    Match each sealant, collar, or device to the approved listed firestop system.

  3. Penetration preparationCritical

    Show annular space, backing material, and substrate before concealment.

  4. Complete sealCritical

    Check the seal around the full penetration and at rated joints.

  5. Inspection accessCritical

    Keep all firestop locations visible until inspection.

Phase #19

Insulation

  1. Wall cavity insulation R-valueCritical

    Match insulation to the approved energy compliance path and plans; confirm whether this building uses the residential or commercial energy provisions.

    FBC-E R402.1.2FBC-E C402.2
  2. Ceiling/attic insulation R-valueCritical

    Match insulation to the approved energy compliance path and plans; confirm whether this building uses the residential or commercial energy provisions.

    FBC-E R402.1.2FBC-E C402.2
  3. Insulation coverage and gapsCritical

    Verify no gaps, voids, or compression in insulation installation

    FBC-E R402.4.1.1FBC-E C402.2
  4. Air sealing

    Verify air sealing at penetrations, top plates, and rim joists

    FBC-E R402.4.1.1FBC-E C402.5
Phase #20

Roof In-Progress

If in scope
  1. Drip edge installationCritical

    Verify drip edge is installed at eaves and rakes

  2. Valley and flashingCritical

    Verify valley flashing and wall flashing are properly installed

  3. Roof penetration sealing

    Verify all roof penetrations are properly sealed and flashed

  4. Covering materialCritical

    Match roof tile, shingles, or metal panels to the approved plans and product approval.

  5. Covering attachmentCritical

    Show fastener or clip pattern before it is concealed by the next course.

  6. Flashing installationCritical

    Show flashing at valleys, walls, edges, and penetrations while accessible.

Phase #21

Exterior Wall Covering (Lath / Stucco / Siding)

If in scope
  1. Wall covering material and installationCritical

    Verify exterior wall covering material matches approved plans and is properly installed

  2. Weather-resistive barrierCritical

    Verify weather-resistive barrier is properly installed behind cladding

  3. Flashing at penetrations and transitionsCritical

    Verify flashing is installed at windows, doors, and wall transitions

  4. Fastener pattern and spacing

    Verify cladding fastener type and spacing per manufacturer and plans

Phase #22

Soffit

If in scope
  1. Soffit material and attachmentCritical

    Verify soffit material matches approved plans and is properly attached

  2. Ventilation openingsCritical

    Verify soffit ventilation openings are properly sized and screened

  3. Continuous coverage

    Verify soffit is installed continuously with no gaps

  4. Fascia attachmentCritical

    Show fascia material and fastening where fascia is included in the permit.

  5. Openings and edgesCritical

    Check soffit attachment at edges, corners, and openings.

Phase #23

Drywall / Gypsum Board

If in scopeBD-Dependent

Most jurisdictions skip this inspection for this project type. Confirm with your building department whether they'll require it.

  1. Drywall thickness and typeCritical

    Match board type, thickness, exposure rating, and layers to the approved rated or shear assembly.

  2. Fastener spacingCritical

    Verify screw or nail spacing meets code requirements

  3. Fire-rated assembliesCritical

    Verify fire-rated walls and ceilings have proper drywall layers per rating

  4. Fire-rated party wall assemblyCritical

    Verify party wall has required layers of Type X gypsum per fire rating (typically 1-hour)

Electrical

Phase #24

Temporary Power

If in scope
  1. Temporary power pole and meterCritical

    Verify temporary power pole is properly set with meter base and disconnect

    NEC 590.4
  2. Grounding electrodeCritical

    Verify grounding rod is installed and connected to temporary panel

    NEC 250.52
  3. GFCI protectionCritical

    Verify all temporary receptacles have GFCI protection

    NEC 590.6
  4. Service equipmentCritical

    Show temporary service equipment, overcurrent protection, and approved location.

  5. Safe installationCritical

    Confirm temporary wiring is supported and protected from damage.

Phase #25

Power Release / Service

If in scope
  1. Service equipment installedCritical

    Show meter enclosure, disconnect, and service conductors ready for utility connection.

  2. Service grounding and bondingCritical

    Show grounding electrode and bonding connections at the service.

  3. Panel and circuit identificationCritical

    Label service and affected panels clearly.

  4. Utility release readinessCritical

    Have the approved service plans and required utility coordination available.

  5. Safe energizationCritical

    Confirm exposed wiring is protected and all covers are installed before release.

Phase #26

Electrical Final

  1. Panel complete and labeledCritical

    Verify panel cover installed, all breakers labeled, no open knockouts

    NEC 408.4NEC 408.7
  2. GFCI and AFCI operationalCritical

    Verify all GFCI and AFCI devices test and reset properly

    NEC 210.8NEC 210.12
  3. Receptacle and switch functionCritical

    Verify outlets and switches operate correctly throughout

  4. Light fixtures installed

    Verify all light fixtures are installed and operational

    NEC 210.70
  5. Exterior lighting and outletsCritical

    Where in scope, demonstrate outdoor GFCI protection and required exterior entrance lighting.

    NEC 210.8NEC 210.70

Plumbing

Phase #27

Plumbing Final

  1. Fixture installation and operationCritical

    For fixtures in the approved scope, show level alignment, water and drainage connections, and live operation.

    FBC-P 405.3FBC-P 301.3FBC-P 301.4
  2. Water heater installationCritical

    Where a water heater is in scope, show the installed relief valve and discharge piping. For a storage-type heater, show a pan only where tank leakage would cause damage. Show the pan drain where required; a replacement needs no new pan drain if none was previously installed (FBC-P 504.7.2).

    FBC-P 504.4FBC-P 504.6FBC-P 504.7FBC-P 504.7.1FBC-P 504.7.2
  3. No visible leaksCritical

    During the live fixture run, show exposed connections and surrounding areas with no visible leaks.

  4. Hose bibbs and exterior plumbing

    Where exterior hose connections are in scope, show backflow protection and operation.

    FBC-P 608.16.4.2

Mechanical

Phase #28

Mechanical Final

  1. System operational testCritical

    Demonstrate the installed system operating in its approved heating, cooling, exhaust, or hood mode as applicable.

  2. Air handler and condenser installationCritical

    If an air handler or condenser is in scope, show installed equipment, clearance, support, and manufacturer labels.

    FBC-M 304.1
  3. Condensate drainCritical

    Where cooling equipment produces condensate, show the drain and approved termination.

    FBC-M 307.2
  4. Duct registers and grilles

    Show supply and return openings and demonstrate airflow at representative locations.

    FBC-M 603.18
  5. Equipment labels and data plates

    Match installed equipment model and rating to approved plans and manufacturer instructions.

    FBC-M 304.1

Building

Phase #29

Roof Final

  1. Roofing material installationCritical

    Verify roofing material is installed per manufacturer specs and approved plans

  2. Flashing completenessCritical

    Verify all flashing is complete at walls, valleys, penetrations, and edges

  3. Ridge vent or ventilation

    Show roof or attic ventilation where the approved design requires it.

  4. Covering attachment evidenceCritical

    Show in-progress evidence for concealed fasteners, clips or adhesive and visible attachment at roof edges and terminations.

  5. Cleanup and debris removal

    Verify job site is clean with no exposed nails or debris in gutters

  6. Completed roofCritical

    Confirm all roof planes, edges, penetrations, and terminations are complete.

Phase #30

Building Final

Typical Final
  1. Egress doors and hardwareCritical

    Verify egress doors provide minimum 32-inch clear width and proper hardware

  2. Smoke alarms installed and operationalCritical

    Show required smoke alarms in affected dwelling units and demonstrate operation.

  3. CO alarms installedCritical

    Verify carbon monoxide alarms where required

  4. Emergency escape openingsCritical

    Verify bedroom windows meet egress size requirements

  5. Stairway complianceCritical

    Verify stair rise, run, handrail height, and landing dimensions

  6. Party wall continuity and sealingCritical

    Show rated separations between units and common areas against the approved assembly, including visible penetrations.

  7. Address numbers visible

    Verify address numbers are posted and visible from street

  8. Exterior finishes complete

    Verify exterior cladding, trim, and weatherproofing are complete

  9. Site grading and drainage

    Show finished grading and drainage against approved site plans; no universal 6-in-10-ft rule.