- #01Plan and document coordination
Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.
FBC-B 107.2.1 - #02Zoning and site coordination
Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #03Floodplain coordination
Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #04Fire-authority coordination
Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
New Single Family Modular Home
Set a state-approved factory-built modular home on a site foundation, join modules, and complete site work and utility crossovers. Do not use for a HUD mobile home.
Last updated: Sep 29, 2026
Section 1
Required Documents
Submit these with your initial project package.
Conditional
- Manufacturer and site construction plansThe manufacturer's building package and plans for foundations, connections, and other work completed on site.WhenFactory-built scope is covered by the manufacturer's building package and site-built scope by plans for foundations, connections, and other on-site work. Documents already in the package count; no duplicate upload is needed.
- Energy documentationEnergy-compliance information applicable to the home and work completed on site.WhenEnergy compliance is not already covered inside the manufacturer's building package. Additional material is requested only when it applies to the on-site work.
- Product documentationApproval documentation applicable to products and components included in the project scope.WhenProducts or components in the project scope have approval documentation that is not already covered by the building package. Factory components do not each need a separate upload.
- Site plan or surveyA site drawing showing the home, its placement, and the proposed site work.WhenYou have a site drawing showing the home, its placement, and the proposed site work. A site plan that shows placement is acceptable; a separate survey is not required because of this label.
Courtesy screen
Courtesy screen on every plan review
Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.
Section 2
Approval criteria for this project type
These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.
BuildingConditional review scope
- #01Footing / foundation designLife Safety
Footing or foundation design must show dimensions, reinforcement, depth, and connection to the structure above.
FBC-R R403FBC-B 1809 - #02Attachment to existing structureLife Safety
Connection details between the new work and the existing structure must show fastener type, spacing, and embedment.
FBC-R R301.1 - #03Plan review applicability (FBC 107.3.5)Documentation
Per FBC-B 107.3.5, manufactured/modular building plans are exempt except for foundations and modifications (Exemption #6). FCC performs this review only when the building department requires plan review or the client opts in.
FBC-B 107.3.5
MechanicalRequired
- #01Combustion air and ventingLife Safety
Fuel-fired equipment requires combustion air and proper venting per FBC-M 303 / 804.
FBC-M 303FBC-M 804FBC-FG 304.1FBC-FG 503 - #02Construction-document clarity — modular-home mechanical connectionsDocumentation
The submitted documents must clearly identify the site-built mechanical connections for the new modular home so FCC can review that mandatory scope as part of the one residential plan review.
FBC-B 107.2.1FBC-B 107.3.5
ElectricalRequired
- #01Service size and load calculationCode
Electrical service and feeder sizing supported by NEC Article 220 load calculation.
NEC 220NEC 230 - #02Construction-document clarity — modular-home electrical serviceDocumentation
The submitted documents must clearly identify the site-built electrical service and connection work for the new modular home so FCC can review that mandatory scope as part of the one residential plan review.
FBC-B 107.2.1FBC-B 107.3.5
Items marked Conditional review scope are non-blocking. Per FBC 107.3.5, plan review isn't required for these scopes — FCC reviews them when the building department requests it or the client wants the extra set of eyes.
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your own inspection list comes from your approved plans. Inspections marked “If in scope” apply only when your plans include that work. Call (772) 222-6679 with questions.
Building
Footing / Grade Beam
If in scope- Footing dimensionsCritical
Verify footing width and depth match approved plans
FBC-R R403.1FBC-R R403.1.1 - Rebar size and spacingCritical
Verify rebar size, spacing, and placement per plans
FBC-R R403.1 - UFER grounding electrodeCritical
Verify minimum 20 feet of #4 bare copper or rebar is encased in footing
NEC 250.52 - Foundation anchorage layout
Verify anchor bolt placement for sill plate attachment
FBC-R R403.1.6
Slab
If in scope- Slab vapor barrierCritical
Verify vapor barrier is installed under slab per plans
FBC-R R506.2.3 - Slab thickness and wire meshCritical
Verify slab thickness and reinforcement per plans
FBC-R R506.1 - Slab forms and elevationCritical
Verify slab outline, thickness, and elevations match the approved plans.
- Under-slab preparationCritical
Show prepared base, penetrations, and required under-slab work before the pour.
- Reinforcing supportCritical
Show slab steel or mesh supported at the planned position and with required laps.
Manufactured Building / Tie-Down
- Foundation and module connectionCritical
Show approved foundation, bearing points, anchors, and module connections before concealment.
FBC-B 110.3 - Module jointsCritical
Show structural joins and weather sealing between modules.
FBC-B 110.3 - Site work and utility crossoversCritical
Show site-installed work and visible utility crossovers against approved plans.
FBC-B 110.3
Electrical
Electrical Rough-In
If in scope- Panel installationCritical
Verify panel rating and overcurrent protection match approved design, with clear working space.
NEC 408.36NEC 110.26 - Wire sizing per circuitsCritical
Verify wire gauge matches breaker amperage for each circuit
NEC 310.16NEC 240.4 - Box fill and installationCritical
Verify electrical boxes are properly installed and not overfilled
NEC 314.16 - GFCI and AFCI locationsCritical
Verify GFCI and AFCI protection is provided where required
NEC 210.8NEC 210.12 - Alarm locations, power provisions and interconnection methodCritical
When alarms are in the approved scope, identify planned smoke and CO alarm locations, exposed smoke-alarm power provisions and the approved wired or listed wireless smoke interconnection method. Record the permitted CO power method; installed devices are checked at final.
FBC-R R314.3FBC-R R314.4FBC-R R314.6FBC-R R315.1FBC-R R315.1.1 - Grounding and bondingCritical
Show grounding electrode system and its approved electrode types and connections.
NEC 250.50NEC 250.52
Mechanical
Mechanical Rough-In
If in scope- Ductwork installationCritical
Verify duct sizes, routing, and support match approved plans
FBC-M 603.1 - Duct sealingCritical
Verify duct joints and connections are properly sealed
FBC-M 603.9 - Equipment placementCritical
Verify air handler and condenser locations per plans with required clearances
FBC-M 304.1 - Refrigerant line installationCritical
Compare refrigerant piping routing and sizing with approved plans; leave field-made joints exposed before concealment.
FBC-M 1107.1FBC-M 1107.7 - Return air pathway
Verify return air pathways are properly sized and located
FBC-M 603.1
Building
Exterior Wall Covering (Lath / Stucco / Siding)
If in scope- Wall covering material and installationCritical
Verify exterior wall covering material matches approved plans and is properly installed
FBC-R R703.1 - Weather-resistive barrierCritical
Verify weather-resistive barrier is properly installed behind cladding
FBC-R R703.2 - Flashing at penetrations and transitionsCritical
Verify flashing is installed at windows, doors, and wall transitions
FBC-R R703.4 - Fastener pattern and spacing
Verify cladding fastener type and spacing per manufacturer and plans
FBC-R R703.1
Soffit
If in scope- Soffit material and attachmentCritical
Verify soffit material matches approved plans and is properly attached
FBC-R R703.1 - Ventilation openingsCritical
Verify soffit ventilation openings are properly sized and screened
FBC-R R806.1 - Continuous coverage
Verify soffit is installed continuously with no gaps
FBC-R R703.1
Electrical
Temporary Power
If in scope- Temporary power pole and meterCritical
Verify temporary power pole is properly set with meter base and disconnect
NEC 590.4 - Grounding electrodeCritical
Verify grounding rod is installed and connected to temporary panel
NEC 250.52 - GFCI protectionCritical
Verify all temporary receptacles have GFCI protection
NEC 590.6
Electrical Final
- Panel complete and labeledCritical
Verify panel cover installed, all breakers labeled, no open knockouts
NEC 408.4 - GFCI and AFCI operationalCritical
Verify all GFCI and AFCI devices test and reset properly
NEC 210.8NEC 210.12 - Receptacle and switch functionCritical
Operate affected receptacles and switches in this permit and show completed connections.
FBC-B 110.3 - Light fixtures installed
Verify all light fixtures are installed and operational
NEC 210.70 - Exterior lighting and outletsCritical
Where this permit changes exterior lighting or outlets, show operation and required GFCI protection.
NEC 210.8NEC 210.70 - Installed alarm devices and operation, if in scopeCritical
When alarm installation is in this permit, confirm installed smoke and CO device locations and labels against the approved plan and permitted power method; demonstrate smoke-alarm interconnection and applicable device tests per manufacturer instructions.
FBC-R R314.3FBC-R R314.4FBC-R R314.6FBC-R R315.1FBC-R R315.1.1
Plumbing
Plumbing Final
If in scopeBD-DependentMost jurisdictions skip this inspection for this project type. Confirm with your building department whether they'll require it.
- Site plumbing connectionCritical
Show the approved water and drain connections between the factory-built home and site utilities.
FBC-B 110.3 - Leak and operation testCritical
Show applicable system test results, then demonstrate site connections operating with no visible leaks.
FBC-P 312.1
Mechanical
Mechanical Final
- System operational testCritical
Demonstrate only the permitted mechanical system operating per approved design and manufacturer instructions.
- Air handler and condenser installationCritical
Where air handler or condenser equipment is in scope, verify installation, access and clearances against approved plans and manufacturer instructions.
FBC-M 304.1 - Condensate drainCritical
Verify condensate drain is properly routed and terminated
FBC-M 307.2 - Duct registers and grillesCritical
Where ducts are in scope, show representative installed registers and grilles per manufacturer instructions.
FBC-M 603.18 - Equipment labels and data plates
Show equipment nameplates and compare capacity and efficiency to the approved schedule.
Building
Building Final
Typical Final- Egress doors and hardwareCritical
Verify egress doors provide minimum 32-inch clear width and proper hardware
FBC-R R311.2 - Smoke alarms installed and operationalCritical
Verify smoke alarms in each bedroom, outside sleeping areas, and each level
FBC-R R314.3 - CO alarms installedCritical
Verify carbon monoxide alarms where required
FBC-R R315.1 - Emergency escape openingsCritical
Verify bedroom windows meet egress size requirements
FBC-R R310.1 - Stairway complianceCritical
Verify stair rise, run, handrail height, and landing dimensions
FBC-R R311.7 - Address numbers visible
Verify address numbers are posted and visible from street
FBC-R R319.1 - Exterior finishes complete
Verify exterior cladding, trim, and weatherproofing are complete
FBC-R R703.1 - Site grading and drainage
Verify finish grade slopes away from foundation minimum 6 inches in 10 feet
FBC-R R401.3
