- #01Plan and document coordination
Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.
FBC-B 107.2.1 - #02Zoning and site coordination
Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #03Floodplain coordination
Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #04Fire-authority coordination
Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
New Townhome
Row homes which have their own address (not a unit number) are townhomes. If each residence has an invididual unit number and shared address, please choose Condo
Last updated: Apr 22, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Construction Plans Sealed by a Florida Registered Design ProfessionalConstruction plans sealed by a Florida-registered design professional (architect or engineer)
- Energy Compliance FormsEnergy compliance documentation per FBC Chapter 13 / IECC
- Product ApprovalsFlorida Product Approvals for windows, doors, roofing materials, and other regulated components
- Site Plan / SurveyCurrent site plan or survey showing property boundaries, setbacks, and building footprint
Conditional
- Truss Engineering & Layout OR Truss Deferral AffidavitTruss engineering package, conventional framing per FBC, or a truss deferral letter requesting deferred submittal of truss engineering.WhenRequired only when structure uses pre-engineered trusses and truss engineering is not shown in the sealed plan set; satisfied by truss engineering in plan set OR conventional framing per FBC OR a truss deferral letter.
Courtesy screen
Courtesy screen on every plan review
Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.
Section 2
Approval criteria for this project type
These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.
BuildingRequired
- #01Design wind speed & exposureLife Safety
Structural drawings must declare design wind speed (Vult) and exposure category matching the jurisdiction's wind speed map.
FBC-R R301.2.1ASCE 7-22 - #02Egress from sleeping roomsLife Safety
Each sleeping room must have an emergency escape and rescue opening meeting R310 dimensions.
FBC-R R310 - #03Smoke and CO alarm coverageLife Safety
Smoke alarms in each sleeping room, outside each sleeping area, and on each story. CO alarms where fuel-fired appliances or attached garages exist.
FBC-R R314FBC-R R315 - #04Structural wall section and load pathLife Safety
A continuous wall section from foundation through roof must show framing, sheathing, connectors, and uplift resistance.
FBC-R R301FBC-R R602FBC-R R802 - #05Townhouse fire-resistance separationLife Safety
Each townhouse must be treated as a separate building and provided with a compliant fire-resistance-rated separation assembly, continuous construction, and protected penetrations.
FBC-R R302.2FBC-R R302.2.1FBC-R R302.2.2FBC-R R302.4 - #06Florida product approvalCode
Florida product approval (FL#) or Miami-Dade NOA must be listed for regulated products (fenestration, structural panels, covering systems).
FBC-B 1708FBC-R R301.2.1.2
MechanicalRequired
- #01Combustion air and ventingLife Safety
Fuel-fired equipment requires combustion air and proper venting per FBC-M 303 / 804.
FBC-M 303FBC-M 804FBC-FG - #02Manual J / S / D load calculationPerformance
HVAC equipment sizing per Manual J; selection per Manual S; duct design per Manual D.
FBC-R M1401.3FBC-M 309 - #03VentilationPerformance
Whole-house or occupancy-based ventilation per FBC-R M1507 / FBC-M 403.
FBC-R M1507FBC-M 403
ElectricalRequired
- #01AFCI and GFCI protectionLife Safety
AFCI protection for dwelling unit branch circuits per NEC 210.12; GFCI per NEC 210.8 at required locations.
NEC 210.8NEC 210.12 - #02Grounding and bondingLife Safety
Grounding electrode, equipment grounding, and bonding per NEC Article 250.
NEC 250 - #03Service size and load calculationCode
Electrical service and feeder sizing supported by NEC Article 220 load calculation.
NEC 220NEC 230
PlumbingRequired
- #01Water service and DWV sizingCode
Water service line sizing and DWV sizing consistent with fixture unit count.
FBC-P 604FBC-P 709FBC-P 906 - #02Backflow preventionCode
Backflow prevention required at well, irrigation, or other cross-connections per FBC-P 608.
FBC-P 608
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your FCC inspector will confirm which apply to your project. Call (772) 222-6679 with questions.
Plumbing
Underground Plumbing
Required- Pipe material and sizingCritical
Verify pipe material and sizes match approved plans
FBC-P 604.1FBC-P 305.1 - Burial depthCritical
Verify underground pipe burial depth meets code minimum
FBC-P 305.5 - Pipe slope and supportCritical
Verify proper slope on drain lines and adequate support
FBC-P 704.1 - Pressure testCritical
Verify plumbing system holds required pressure test
FBC-P 312.2 - Cleanout locations
Verify cleanout access points are installed per plans
FBC-P 708.1
Electrical
Underground Electrical
Conditional- Conduit installationCritical
Verify conduit material, size, and routing per plans
NEC 300.5 - Burial depthCritical
Verify conduit burial depth meets code minimum
NEC 300.5 - UFER ground connectionCritical
Verify UFER grounding electrode is properly connected to rebar in footing
NEC 250.52(A)(3) - Conduit protection
Verify conduit is protected from damage where exposed
NEC 300.5(D)
Building
Footing, Slab, UFER
Required- Footing dimensionsCritical
Verify footing width and depth match approved plans
FBC-R R403.1FBC-R R403.1.1 - Rebar size and spacingCritical
Verify rebar size, spacing, and placement per plans
FBC-R R403.1 - UFER grounding electrodeCritical
Verify minimum 20 feet of #4 bare copper or rebar is encased in footing
NEC 250.52(A)(3) - Slab vapor barrierCritical
Verify vapor barrier is installed under slab per plans
FBC-R R506.2.3 - Slab thickness and wire meshCritical
Verify slab thickness and reinforcement per plans
FBC-R R506.1 - Foundation anchorage layout
Verify anchor bolt placement for sill plate attachment
FBC-R R403.1.6
Fill Cell, Tie Beam, Lintel
Conditional- Cell fill and groutCritical
Verify cells are properly grouted per plans
FBC-R R609.1.1 - Tie beam reinforcementCritical
Verify tie beam rebar size, spacing, and lap splices per plans
FBC-R R609.1 - Lintel reinforcementCritical
Verify lintel rebar and sizing over openings per plans
FBC-R R609.7 - Vertical rebar placementCritical
Verify vertical rebar is properly placed and spaced in block wall
FBC-R R609.1
Rough Framing
Required- Wall stud spacing and sizeCritical
Verify stud size and spacing match approved plans
FBC-R R602.3FBC-R R602.3.1 - Headers and beamsCritical
Verify header and beam sizes over openings per plans
FBC-R R602.7 - Top and bottom plate connectionsCritical
Verify double top plates with proper lapping and anchored bottom plates
FBC-R R602.3.2 - Corner and intersection bracingCritical
Verify proper bracing at corners and wall intersections
FBC-R R602.10 - Window and door rough openingsCritical
Verify rough openings match approved plans for size and location
FBC-R R602.7 - Hurricane straps and hold-downsCritical
Verify hurricane straps and hold-down hardware installed per plans
FBC-R R802.11 - Fire blocking
Verify fire blocking is installed at required locations
FBC-R R602.8 - Fire separation wall framingCritical
Verify party/fire wall is framed continuously from foundation to underside of roof sheathing per plans
FBC-R R302.1FBC-R R302.2 - Draft stopping in party wallCritical
Verify draft stopping is installed in concealed spaces of the fire separation wall
FBC-R R302.4
Roof Sheathing
Conditional- Roof sheathing attachmentCritical
Verify roof deck nailing pattern and edge spacing per the approved nailing schedule.
FBC-R R803.2FBC-R R802.11 - Roof sheathing material and thicknessCritical
Verify roof sheathing panel material, thickness, and span rating match the approved plans.
FBC-R R803.1 - Panel gap spacing at roof deck
Verify proper edge gap between roof sheathing panels per the panel manufacturer.
FBC-R R803.2
Wall Sheathing
Conditional- Wall sheathing attachmentCritical
Verify wall sheathing nailing pattern and edge spacing per the approved nailing schedule (shear wall zones often require tighter spacing).
FBC-R R602.3 - Wall sheathing material and thicknessCritical
Verify wall sheathing panel material, thickness, and grade stamp match the approved plans.
FBC-R R602.3 - Panel gap spacing at walls
Verify proper edge gap between wall sheathing panels per the panel manufacturer.
FBC-R R602.3
Truss Tie Down and Engineering
Required- Truss spacing and alignmentCritical
Verify truss spacing and alignment match approved plans
FBC-R R802.10 - Truss-to-wall connectionCritical
Verify hurricane clips or straps at every truss-to-wall connection
FBC-R R802.11 - Truss bracingCritical
Verify lateral and diagonal bracing is installed per truss engineering
FBC-R R802.10.3 - Truss engineering on siteCritical
Verify sealed truss engineering package is available and matches installed trusses
FBC-R R802.10.1 - Gable end bracing
Verify gable end trusses are properly braced
FBC-R R802.10.3
Roof Dry In, In Progress
Required- Underlayment installationCritical
Verify roof underlayment is installed per code and manufacturer specs
FBC-R R905.1.1 - Drip edge installationCritical
Verify drip edge is installed at eaves and rakes
FBC-R R905.2.8.5 - Valley and flashingCritical
Verify valley flashing and wall flashing are properly installed
FBC-R R903.2 - Roof penetration sealing
Verify all roof penetrations are properly sealed and flashed
FBC-R R903.2
Plumbing
Rough Plumbing
Required- Supply pipe sizing and materialCritical
Verify supply pipe sizes and material match approved plans
FBC-P 604.1 - DWV pipe sizing and slopeCritical
Verify drain, waste, and vent pipe sizes and slope per plans
FBC-P 704.1 - Pipe support and hangingCritical
Verify pipes are properly supported at required intervals
FBC-P 308.1 - Vent termination locations
Verify vent pipes terminate properly through roof
FBC-P 903.1 - Water heater rough-in
Verify water heater location, drain pan, and connections per plans
FBC-P 607.1
Electrical
Rough Electrical
Required- Panel installationCritical
Verify electrical panel is properly mounted and sized per plans
NEC 408.4 - Wire sizing per circuitsCritical
Verify wire gauge matches breaker amperage for each circuit
NEC 210.3NEC 240.4 - Box fill and installationCritical
Verify electrical boxes are properly installed and not overfilled
NEC 314.16 - GFCI and AFCI locationsCritical
Verify GFCI and AFCI protection is provided where required
NEC 210.8NEC 210.12 - Smoke and CO alarm wiringCritical
Verify interconnected smoke and CO alarm wiring is in place
FBC-R R314.3FBC-R R315 - Grounding and bondingCritical
Verify grounding electrode system and bonding connections
NEC 250.50
Mechanical
Rough Mechanical/HVAC
Required- Ductwork installationCritical
Verify duct sizes, routing, and support match approved plans
FBC-M 603.1 - Duct sealingCritical
Verify duct joints and connections are properly sealed
FBC-M 603.9 - Equipment placementCritical
Verify air handler and condenser locations per plans with required clearances
FBC-M 304.1 - Refrigerant line installation
Verify refrigerant line sizing and insulation per plans
FBC-M 1101.3 - Return air pathway
Verify return air pathways are properly sized and located
FBC-M 601.2
Building
Insulation
Required- Wall cavity insulation R-valueCritical
Verify wall insulation R-value matches energy calculations
FBC-E R402.1 - Ceiling/attic insulation R-valueCritical
Verify ceiling or attic insulation R-value per energy calculations
FBC-E R402.1 - Insulation coverage and gapsCritical
Verify no gaps, voids, or compression in insulation installation
FBC-E R402.4 - Air sealing
Verify air sealing at penetrations, top plates, and rim joists
FBC-E R402.4.1
Lathe, Siding
Conditional- Wall covering material and installationCritical
Verify exterior wall covering material matches approved plans and is properly installed
FBC-R R703.1 - Weather-resistive barrierCritical
Verify weather-resistive barrier is properly installed behind cladding
FBC-R R703.2 - Flashing at penetrations and transitionsCritical
Verify flashing is installed at windows, doors, and wall transitions
FBC-R R703.4 - Fastener pattern and spacing
Verify cladding fastener type and spacing per manufacturer and plans
FBC-R R703.1
Drywall
ConditionalBD-DependentMost jurisdictions skip this inspection for this project type. Confirm with your building department whether they'll require it.
- Drywall thickness and typeCritical
Verify drywall thickness matches plans, moisture-resistant board in wet areas
FBC-R R702.3.1 - Fastener spacingCritical
Verify screw or nail spacing meets code requirements
FBC-R R702.3.5 - Fire-rated assembliesCritical
Verify fire-rated walls and ceilings have proper drywall layers per rating
FBC-R R302.6 - Moisture barrier in wet areas
Verify moisture barrier behind tub/shower surrounds where required
FBC-R R702.4 - Fire-rated party wall assemblyCritical
Verify party wall has required layers of Type X gypsum per fire rating (typically 1-hour)
FBC-R R302.1FBC-R R302.2 - Party wall penetration firestoppingCritical
Verify all penetrations through party wall are firestopped with approved materials
FBC-R R302.4
Electrical
Final Electrical
RequiredTypical Final- Panel complete and labeledCritical
Verify panel cover installed, all breakers labeled, no open knockouts
NEC 408.4 - GFCI and AFCI operationalCritical
Verify all GFCI and AFCI devices test and reset properly
NEC 210.8NEC 210.12 - Receptacle and switch functionCritical
Verify outlets and switches operate correctly throughout
NEC 210.52 - Light fixtures installed
Verify all light fixtures are installed and operational
NEC 210.70 - Exterior lighting and outletsCritical
Verify exterior outlets are GFCI protected and lighting is functional
NEC 210.8NEC 210.52(E)
Plumbing
Final Plumbing
RequiredTypical Final- Fixture installation and operationCritical
Verify all plumbing fixtures are installed, connected, and operational
FBC-P 405.1 - Water heater installationCritical
Verify water heater is properly installed with TPR valve, drain pan, and discharge pipe
FBC-P 607.1 - No visible leaksCritical
Verify no leaks at any supply or drain connection
FBC-P 312.1 - Hose bibbs and exterior plumbing
Verify exterior hose bibbs have backflow prevention
FBC-P 608.15.4.2
Mechanical
Final Mechanical/HVAC
RequiredTypical Final- System operational testCritical
Verify HVAC system starts, runs, and produces heated and cooled air
FBC-M 304.1 - Air handler and condenser installationCritical
Verify equipment is properly installed with required clearances and level
FBC-M 304.1 - Condensate drainCritical
Verify condensate drain is properly routed and terminated
FBC-M 307.2 - Duct registers and grilles
Verify all supply and return registers are installed and operational
FBC-M 601.2 - Equipment labels and data plates
Verify equipment nameplates match approved plans for capacity and efficiency
FBC-M 304.1
Building
Final Building
RequiredTypical Final- Egress doors and hardwareCritical
Verify egress doors provide minimum 32-inch clear width and proper hardware
FBC-R R311.2 - Smoke alarms installed and operationalCritical
Verify smoke alarms in each bedroom, outside sleeping areas, and each level
FBC-R R314.3 - CO alarms installedCritical
Verify carbon monoxide alarms where required
FBC-R R315 - Emergency escape openingsCritical
Verify bedroom windows meet egress size requirements
FBC-R R310.1 - Stairway complianceCritical
Verify stair rise, run, handrail height, and landing dimensions
FBC-R R311.7 - Party wall continuity and sealingCritical
Verify fire separation wall is complete with no unsealed penetrations, gaps, or breaches from foundation to roof
FBC-R R302.1FBC-R R302.2FBC-R R302.4 - Address numbers visible
Verify address numbers are posted and visible from street
FBC-R R319.1 - Exterior finishes complete
Verify exterior cladding, trim, and weatherproofing are complete
FBC-R R703.1 - Site grading and drainage
Verify finish grade slopes away from foundation minimum 6 inches in 10 feet
FBC-R R401.3