- #01Plan and document coordination
Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.
FBC-B 107.2.1 - #02Zoning and site coordination
Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #03Floodplain coordination
Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #04Fire-authority coordination
Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
Single Family Alteration
Change an existing home structure, layout, or building systems without adding floor area. Use Repair/Remodel for finish-only work and a dedicated trade type for a single-trade permit.
Last updated: Sep 29, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Construction PlansConstruction plans reflecting the full scope of alteration work. Plans prepared by a Florida-registered architect or engineer carry that professional's seal. Plans prepared by a contractor or owner are accepted without a seal unless Florida law or the building department requires professional plans.
Conditional
- Scope of Work DescriptionVery detailed written scope of work describing all work to be performedWhenThe scope of work you type on the submission form counts. A separate document is not needed.
- Product ApprovalsFlorida Product Approvals for any regulated components being installedWhenRequired if installing new windows, doors, roofing, or other regulated products
Courtesy screen
Courtesy screen on every plan review
Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.
Section 2
Approval criteria for this project type
These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.
BuildingRequired
- #01Structural impact of scope (load-bearing walls)Life Safety
If scope includes removing or modifying load-bearing walls, verify new beam/header design is provided.
FBC-EB 503.3FBC-R R301FBC-R R301.1.3 - #02Existing condition compliance (egress, smoke alarms, CO alarms)Life Safety
For work affecting bedrooms or sleeping areas, verify existing emergency egress and smoke/CO alarms meet or are upgraded to current code.
FBC-EB 703.2FBC-R R310FBC-R R314FBC-R R315 - #03Window/door replacement wind complianceLife Safety
If scope includes window or door replacement, verify product approvals (FL#, NOA, or F.S. 553.8425 local approval) for wind and HVHZ if applicable.
F.S. 553.842F.S. 553.8425Rule 61G20-3 F.A.C.FBC-R R609.3FBC-R R301.2.1.2
MechanicalConditional review scope
- #01HVAC equipment changeoutPerformance
If HVAC changeout or new system is in scope, verify equipment schedule with capacity matches scope.
FBC-E R403
ElectricalConditional review scope
- #01AFCI/GFCI upgrade in work areaLife Safety
If scope includes electrical work in kitchens, bathrooms, bedrooms, or wet locations, verify AFCI/GFCI coverage.
NEC 210.8NEC 210.12
PlumbingConditional review scope
- #01Fixture additions in remodel scopeDocumentation
If scope adds or relocates plumbing fixtures (kitchen, bathroom remodel), verify basic fixture layout and water heater adequacy are noted.
FBC-P 701FBC-P 901
Items marked Conditional review scope are non-blocking. Per FBC 107.3.5, plan review isn't required for these scopes — FCC reviews them when the building department requests it or the client wants the extra set of eyes.
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your own inspection list comes from your approved plans. Inspections marked “If in scope” apply only when your plans include that work. Call (772) 222-6679 with questions.
Building
Framing
If in scope- Wall stud spacing and sizeCritical
Verify stud size and spacing match approved plans
FBC-R R602.3 - Headers and beamsCritical
Verify header and beam sizes over openings per plans
FBC-B 110.3 - Top and bottom plate connectionsCritical
Verify plate configuration, laps and anchorage against the approved framing design; do not assume double top plates.
FBC-B 110.3 - Corner and intersection bracingCritical
Verify proper bracing at corners and wall intersections
FBC-B 110.3 - Window and door rough openingsCritical
Verify rough openings match approved plans for size and location
FBC-B 110.3 - Hurricane straps and hold-downsCritical
Compare roof-to-wall connectors and straps with the approved high-wind design and connector schedule.
FBC-R R301.2.1.1 - Fire blockingCritical
Verify fire blocking is installed at required locations
FBC-R R302.11
Roof Dry-In
If in scope- Underlayment installationCritical
Verify roof underlayment is installed per code and manufacturer specs
FBC-R R905.1.1
Plumbing
Plumbing Rough-In
If in scope- Supply pipe sizing and materialCritical
Compare supply pipe material with plans and sizing with approved water-distribution design.
FBC-P 604.3FBC-P 605.4 - DWV pipe sizing and slopeCritical
Compare DWV pipe sizes with approved plans and measure horizontal drain slope.
FBC-P 704.1 - Pipe support and hangingCritical
Verify pipes are properly supported at required intervals
FBC-P 308.1 - Vent termination locationsCritical
Verify the vent terminates outdoors through an approved roof or sidewall method shown on plans.
FBC-P 903.1 - Water heater rough-inCritical
Where a water heater is in scope, compare location and connections with approved plans and instructions; show pan where leakage could cause damage.
FBC-P 502.1FBC-P 504.7
Electrical
Electrical Rough-In
If in scope- Panel installationCritical
Verify panel rating and overcurrent protection match approved design, with clear working space.
NEC 408.36NEC 110.26 - Wire sizing per circuitsCritical
Verify wire gauge matches breaker amperage for each circuit
NEC 310.16NEC 240.4 - Box fill and installationCritical
Verify electrical boxes are properly installed and not overfilled
NEC 314.16 - GFCI and AFCI locationsCritical
Verify GFCI and AFCI protection is provided where required
NEC 210.8NEC 210.12 - Alarm locations, power provisions and interconnection methodCritical
When alarms are in the approved scope, identify planned smoke and CO alarm locations, exposed smoke-alarm power provisions and the approved wired or listed wireless smoke interconnection method. Record the permitted CO power method; installed devices are checked at final.
FBC-R R314.3FBC-R R314.4FBC-R R314.6FBC-R R315.1FBC-R R315.1.1 - Grounding and bondingCritical
Show grounding electrode system and its approved electrode types and connections.
NEC 250.50NEC 250.52
Mechanical
Mechanical Rough-In
If in scope- Ductwork installationCritical
Verify duct sizes, routing, and support match approved plans
FBC-M 603.1 - Duct sealingCritical
Verify duct joints and connections are properly sealed
FBC-M 603.9 - Equipment placementCritical
Verify air handler and condenser locations per plans with required clearances
FBC-M 304.1 - Refrigerant line installationCritical
Compare refrigerant piping routing and sizing with approved plans; leave field-made joints exposed before concealment.
FBC-M 1107.1FBC-M 1107.7 - Return air pathway
Verify return air pathways are properly sized and located
FBC-M 603.1
Building
Insulation
If in scope- Wall cavity insulation R-valueCritical
Verify wall insulation R-value matches energy calculations
FBC-E R402.1.2 - Ceiling/attic insulation R-valueCritical
Verify ceiling or attic insulation R-value per energy calculations
FBC-E R402.1.2 - Insulation coverage and gapsCritical
Verify no gaps, voids, or compression in insulation installation
FBC-E R402.4.1.1 - Air sealingCritical
Verify air sealing at penetrations, top plates, and rim joists
FBC-E R402.4.1.1
Roof In-Progress
If in scope- Drip edge installationCritical
Verify drip edge is installed at eaves and rakes
FBC-R R905.2.8.5 - Valley and flashingCritical
Verify valley flashing and wall flashing are properly installed
FBC-R R903.2 - Roof penetration sealing
Verify all roof penetrations are properly sealed and flashed
FBC-R R903.2 - Covering materialCritical
Match roof tile, shingles, or metal panels to the approved plans and product approval.
- Covering attachmentCritical
Show fastener or clip pattern before it is concealed by the next course.
- Flashing installationCritical
Show flashing at valleys, walls, edges, and penetrations while accessible.
Exterior Wall Covering (Lath / Stucco / Siding)
If in scope- Wall covering material and installationCritical
Verify exterior wall covering material matches approved plans and is properly installed
FBC-R R703.1 - Weather-resistive barrierCritical
Verify weather-resistive barrier is properly installed behind cladding
FBC-R R703.2 - Flashing at penetrations and transitionsCritical
Verify flashing is installed at windows, doors, and wall transitions
FBC-R R703.4 - Fastener pattern and spacing
Verify cladding fastener type and spacing per manufacturer and plans
FBC-R R703.1
Drywall / Gypsum Board
If in scopeBD-DependentMost jurisdictions skip this inspection for this project type. Confirm with your building department whether they'll require it.
- Board product and exposureCritical
Compare board type and thickness with the approved assembly; use an approved tub/shower backer and do not use water-resistant gypsum in direct water exposure.
FBC-R R702.3.7.1FBC-R R702.4.2 - Fastener spacingCritical
Verify screw or nail spacing meets code requirements
FBC-R R702.3.5 - Fire-rated assembliesCritical
Where the garage-to-dwelling separation is in scope, compare gypsum layers, fastening and openings to the approved assembly.
FBC-R R302.6
Electrical
Electrical Final
If in scope- Panel complete and labeledCritical
Verify panel cover installed, all breakers labeled, no open knockouts
NEC 408.4 - GFCI and AFCI operationalCritical
Verify all GFCI and AFCI devices test and reset properly
NEC 210.8NEC 210.12 - Receptacle and switch functionCritical
Operate affected receptacles and switches in this permit and show completed connections.
FBC-B 110.3 - Light fixtures installed
Verify all light fixtures are installed and operational
NEC 210.70 - Exterior lighting and outletsCritical
Where this permit changes exterior lighting or outlets, show operation and required GFCI protection.
NEC 210.8NEC 210.70 - Installed alarm devices and operation, if in scopeCritical
When alarm installation is in this permit, confirm installed smoke and CO device locations and labels against the approved plan and permitted power method; demonstrate smoke-alarm interconnection and applicable device tests per manufacturer instructions.
FBC-R R314.3FBC-R R314.4FBC-R R314.6FBC-R R315.1FBC-R R315.1.1
Plumbing
Plumbing Final
If in scope- Fixture setting and alignmentCritical
Verify in-scope fixtures are set level and aligned.
FBC-P 405.3 - Fixture connections and operationCritical
Show affected fixtures connected to water and drainage systems, then demonstrate operation and check for visible leaks.
FBC-P 301.3FBC-P 301.4 - Water heater installationCritical
If a storage heater is in scope, show installation, relief valve and discharge, and pan/drain where leakage could cause damage.
FBC-P 502.1FBC-P 504.4FBC-P 504.6FBC-P 504.7 - No visible leaksCritical
Run affected fixtures or equipment and show new visible supply and drain connections remain dry.
- Hose bibbs and exterior plumbingCritical
Verify exterior hose bibbs have backflow prevention
FBC-P 608.16.4.2
Mechanical
Mechanical Final
If in scope- System operational testCritical
Demonstrate only the permitted mechanical system operating per approved design and manufacturer instructions.
- Air handler and condenser installationCritical
Where air handler or condenser equipment is in scope, verify installation, access and clearances against approved plans and manufacturer instructions.
FBC-M 304.1 - Condensate drainCritical
Verify condensate drain is properly routed and terminated
FBC-M 307.2 - Duct registers and grillesCritical
Where ducts are in scope, show representative installed registers and grilles per manufacturer instructions.
FBC-M 603.18 - Equipment labels and data plates
Show equipment nameplates and compare capacity and efficiency to the approved schedule.
Building
Building Final
Typical Final- Completed altered scopeCritical
Show each changed structural, layout, and finish element against approved plans.
FBC-B 110.3 - Affected egress and safetyCritical
If this work changes a bedroom, exit, or stair, show the resulting safe route and openings.
FBC-R R310.1FBC-R R311.7 - Affected rated or exterior assembliesCritical
If work disturbs the garage-to-dwelling separation or exterior weather barrier, show the restored approved detail.
FBC-R R302.6FBC-R R703.4
