- #01Plan and document coordination
Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.
FBC-B 107.2.1 - #02Zoning and site coordination
Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #03Floodplain coordination
Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #04Fire-authority coordination
Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
Single Family Aluminum Structure with Shed
Aluminum carport or cover with an integrated shed as part of the same structure.
Last updated: Apr 20, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Construction Plans Sealed by a Florida Registered Design ProfessionalConstruction plans sealed by a Florida-registered design professional showing layout/framing plus wind load criteria and anchor method.
- Product ApprovalsFlorida Product Approvals for structural components.
- Site Plan / SurveySite plan or survey showing property boundaries, setbacks, and structure footprint.
Courtesy screen
Courtesy screen on every plan review
Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.
Section 2
Approval criteria for this project type
These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.
BuildingRequired
- #01Design wind speed & exposureLife Safety
Structural drawings for the aluminum structure and shed must declare the design wind speed (Vult) and exposure category required for the project location.
FBC-R R301.2.1ASCE 7-22 - #02Footing / foundation designLife Safety
Footing or foundation details must support the aluminum structure and shed and show dimensions, reinforcement, depth, and connection to the structure above.
FBC-R R403FBC-B 1809 - #03Attachment and anchorage detailsLife Safety
Connections within the aluminum-and-shed assembly and to any existing residence or foundation must show the primary fastener type, spacing, embedment, and continuous load path.
FBC-B 2002.5FBC-R R301.1 - #04Egress from enclosed areaLife Safety
Where the combined structure encloses or affects an egress path from the residence or a sleeping room, the plans must preserve compliant egress.
FBC-R R310FBC-R R311 - #05Florida product approvalsCode
Florida product approval (FL#) or Miami-Dade NOA information must be listed for regulated fenestration, structural panels, and covering systems used in either portion of the combined structure.
FBC-B 1708FBC-R R301.2.1.2 - #06Engineer of record sealDocumentation
Structural drawings and calculations for the combined aluminum structure and shed must bear the seal and signature of a current Florida-licensed engineer.
Florida Statutes Chapter 471FBC-B 107.3.5
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your FCC inspector will confirm which apply to your project. Call (772) 222-6679 with questions.
Building
Rough Framing
Required- Wall framing and stud spacingCritical
Verify wall stud size, spacing, and layout match approved plans for the shed portion
FBC-R R602.3FBC-R R602.3.1 - Header and beam sizingCritical
Verify headers over openings and beams match approved plans
FBC-R R602.7 - Top and bottom plate connectionsCritical
Verify top plates are doubled and bottom plates are properly anchored
FBC-R R602.3.2 - Roof framing and rafter/truss connectionsCritical
Verify roof framing members are properly sized, spaced, and connected per plans
FBC-R R802.3FBC-R R802.10 - Shed to aluminum structure connectionCritical
Verify the attachment between the framed shed and the aluminum carport structure per engineering
FBC-B 2002.1 - Hurricane straps and tie-downsCritical
Verify hurricane straps or tie-downs are installed at roof-to-wall connections per plans
FBC-R R802.11 - Sheathing attachment
Verify wall and roof sheathing is properly nailed per schedule
FBC-R R602.3FBC-R R803.2
Final Building
RequiredTypical Final- Base rail attachment and tapcon spacingCritical
Verify base rail is secured with tapcons at correct spacing per plans
FBC-B 2002.1FBC-B 2002.4 - Post to base connectionCritical
Verify structural connection of posts to base rail
FBC-B 2002.1 - Post to roof beam connectionCritical
Verify structural connection of posts to roof beams
FBC-B 2002.1 - Gusset connectionsCritical
Verify gusset plates are installed at structural joints per plans
FBC-B 2002.1FBC-B 2002.4 - Beam to gutter connectionCritical
Verify beams are properly connected to gutter system
FBC-B 2002.1 - Gutter clips
Verify gutter clips are installed at proper intervals
FBC-B 2002.1 - Overall structureCritical
Verify overall shape and construction matches approved plans
FBC-B 2002.4 - Screen door opening mechanism height
Verify door latch/opening mechanism is at 54 inch height where pool barrier applies
NEC 680.26FBC-R R303 - Pool equipment bonding
If pool equipment is present, verify bonding wire at pool equipment and at structure
NEC 680.26 - Elite roof panel sealing
If elite (solid) roof panels are present, verify sealing is complete
FBC-B 2002.5
