- #01Plan and document coordination
Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.
FBC-B 107.2.1 - #02Zoning and site coordination
Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #03Floodplain coordination
Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #04Fire-authority coordination
Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
Single Family Battery Storage Installation
Battery energy storage installation, such as a Tesla Powerwall, with or without solar, including the inverter, disconnects, and wiring.
Last updated: Sep 29, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Electrical Plans or Detailed Scope of WorkElectrical plans or a detailed scope of work, including a single-line diagram showing the battery, inverter, and disconnects
- Equipment SpecificationsManufacturer spec sheet with the UL 9540 listing and kWh capacity
- Installation Location PlanPlan showing the installation location and clearances
Courtesy screen
Courtesy screen on every plan review
Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.
Section 2
Approval criteria for this project type
These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.
ElectricalRequired
- #01AFCI and GFCI protectionLife Safety
AFCI protection for dwelling unit branch circuits per NEC 210.12; GFCI per NEC 210.8 at required locations.
NEC 210.8NEC 210.12 - #02Energy storage system listing and installationLife Safety
The energy storage system must be listed to UL 9540 and installed per NEC Article 706, including its inverter connections and disconnecting means.
NEC 706UL 9540 - #03Residential energy storage location, size, and separationLife Safety
A single-family energy storage system must meet the location, size, and separation limits of the Florida Building Code, Residential, Section R328 (Energy Storage Systems).
FBC-R R328 - #04Service size and load calculationCode
Electrical service and feeder sizing supported by NEC Article 220 load calculation.
NEC 220NEC 230 - #05Construction-document clarity — battery storage installation permitDocumentation
The submitted documents must clearly identify the battery storage installation work so FCC can review this mandatory single-family electrical trade as part of the one residential plan review.
FBC-B 107.2.1
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your own inspection list comes from your approved plans. Inspections marked “If in scope” apply only when your plans include that work. Call (772) 222-6679 with questions.
Electrical
Electrical Rough-In
If in scope- Battery wiring before concealmentCritical
Show new ESS conductors, raceways, protection, and terminations before walls close.
NEC 706.31NEC 706.50 - Equipment location and accessCritical
Show the planned ESS location, working space, and manufacturer installation detail.
NEC 110.26NEC 706.20
Electrical Final
Typical Final- ESS installed and labeledCritical
Show listed ESS label, installed components, and approved one-line; compare with manufacturer instructions.
NEC 706.5NEC 706.15 - Disconnect accessCritical
Show accessible ESS disconnect and demonstrate the identified switch.
NEC 706.15 - Circuit protectionCritical
Show ESS circuit overcurrent protection and affected panel directory.
NEC 706.31NEC 408.4 - OperationCritical
Demonstrate normal start, stop, and status against the approved system and manufacturer commissioning instructions.