- #01Plan and document coordination
Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.
FBC-B 107.2.1 - #02Zoning and site coordination
Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #03Floodplain coordination
Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #04Fire-authority coordination
Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
Single Family Demolition
Demolish an existing home, duplex, or townhouse. Inspect utility disconnections before work and the cleared site afterward.
Last updated: Sep 29, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Demolition Plan or Detailed Scope of WorkDemolition plan or detailed written scope of work describing all demolition activities
Conditional
- Site Plan / SurveySite plan or survey showing structures to be demolished and surrounding featuresWhenA survey, site sketch, or marked aerial showing what is being demolished (FBC 107.2.6). Not needed to start review.
- Asbestos SurveyAsbestos survey guidance based on year built and risk; verify requirement during downstream review as needed.WhenGuidance only (non-blocking at intake): may be required depending on year built and asbestos risk factors.
Courtesy screen
Courtesy screen on every plan review
Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.
Section 2
Approval criteria for this project type
These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.
BuildingConditional review scope
- #01Asbestos / lead paint assessmentLife Safety
Pre-demolition asbestos survey is required by federal NESHAP rules for most structures. Lead paint assessment required for pre-1978 dwellings disturbing painted surfaces.
40 CFR 61 Subpart M40 CFR 745 (RRP Rule)FBC-B 105.9 - #02Adjacent property protection and utility disconnectsLife Safety
Demolition plan should identify utility disconnect responsibilities and adjacent-property protection for shared walls or close structures.
FBC-EB 1502Local demolition standards - #03Plan review applicability (FBC 107.3.5)Documentation
FBC-B 107.3.5 identifies asbestos removal as the only minimum plan review criterion for demolition. Full plan review for SF demolition is typically BD-discretionary. FCC performs this review only when the building department requires plan review or the client opts in.
FBC-B 107.3.5
Items marked Conditional review scope are non-blocking. Per FBC 107.3.5, plan review isn't required for these scopes — FCC reviews them when the building department requests it or the client wants the extra set of eyes.
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your own inspection list comes from your approved plans. Inspections marked “If in scope” apply only when your plans include that work. Call (772) 222-6679 with questions.
Building
Demolition (Utilities Disconnected)
- Utility disconnectionsCritical
Document that electrical, gas, water, sewer, and other affected services are disconnected and secured.
FBC-B 110.3 - Work area controlsCritical
Show the demolition area, protection, and separation from structures to remain.
FBC-B 110.3 - Demolition planCritical
Have the approved demolition scope and any required utility clearances available.
FBC-B 110.3 - Hazard protectionCritical
Show protection of adjacent property, public access, and remaining utilities.
FBC-B 110.3
Demolition Final
Typical Final- Removal completeCritical
Confirm all structures and materials in the approved demolition scope are removed.
FBC-B 110.3 - Debris clearedCritical
Show debris and abandoned materials removed from the site.
FBC-B 110.3 - Site made safeCritical
Show open excavations filled or protected and remaining utilities secured.
FBC-B 110.3 - Final site conditionCritical
Show grading and drainage consistent with the approved demolition scope.
FBC-B 110.3