- #01Plan and document coordination
Obvious clerical, title-block, sheet-index, permit-description, or cross-sheet inconsistencies visible in the submitted documents. A Courtesy Comment on these items does not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope.
FBC-B 107.2.1 - #02Zoning and site coordination
Apparent setback, lot-coverage, use, or site-dimension conflicts visible in the submitted plans that could cause the plans to fail Planning and Zoning review. Planning and Zoning makes the zoning and lot-compliance determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #03Floodplain coordination
Apparent inconsistencies or missing coordination in flood-zone, design-flood-elevation, finished-floor, or flood-opening information shown on the plans that could cause the plans to fail floodplain review. The floodplain administrator makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
- #04Fire-authority coordination
Apparent separately reviewed fire alarm, sprinkler, hood-suppression, smoke-control, or similar coordination issues visible on the plans that could cause the plans to fail fire review. The fire marshal makes the determination. The absence of a Courtesy Comment is not approval of those separate requirements.
Single Family Pool Construction
Last updated: Apr 20, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Construction Plans Sealed by a Florida Registered Design ProfessionalPool construction plans showing layout, dimensions, structural details, plumbing, and electrical
- TDH CalculationsTurnover, Design, and Hydraulic (TDH) calculations for the pool system
- Equipment SpecificationsManufacturer specifications for pump, filter, heater, and other pool equipment
- Site Plan / SurveySite plan or survey showing pool location, setbacks, and safety barrier locations
Conditional
- Safety Barrier AffidavitSigned affidavit confirming pool safety barrier and alarm compliance when those details are not shown in sealed construction plans.WhenRequired only if sealed construction plans do not clearly specify pool safety barrier and alarm details.
Courtesy screen
Courtesy screen on every plan review
Every plan FCC reviews receives a limited courtesy screen for the items below when they are reasonably visible in the submitted documents. If we see an apparent issue that could cause the plans to fail review by another agency, we will identify it as a Courtesy Comment. Courtesy Comments alone do not cause FCC to fail or return the plan set unless the same condition also creates a building-code compliance issue within FCC's review scope. The responsible agency makes the final determination—for example, Planning and Zoning for setbacks, lot coverage, use, and other lot-compliance matters. The absence of a Courtesy Comment is not approval of those separate requirements.
Section 2
Approval criteria for this project type
These are the building-code criteria FCC uses to determine the plan-review result. An unresolved item may be issued as a Required Correction and cause the plan set to be returned for correction.
BuildingRequired
- #01Pool barrier complianceLife Safety
Verify a code-compliant pool barrier is shown on plans - height, clearances, gate self-closing/self-latching hardware, and door alarms on dwelling openings facing pool.
ISPSC 305FBC-R R4501.17Florida Statutes 515.27 - #02Pool shell structural designLife Safety
Verify pool shell engineering is provided with soil bearing, reinforcement, and shell thickness.
ISPSC 307FBC-R R403ACI 318 - #03Deck and coping designCode
Verify pool deck slopes, slip resistance, and coping connection are noted.
ISPSC 306FBC-R R326 - #04Setbacks from property lines and structuresCode
Verify pool meets jurisdictional setback requirements from property lines, septic fields, and easements.
ISPSC 305.3Local zoning ordinance - #05Engineer seal on structuralDocumentation
Confirm pool structural drawings bear a current Florida-licensed engineer seal.
Florida Statutes Chapter 471
MechanicalConditional review scope
- #01Pool heater clearances (if gas)Life Safety
If a gas pool heater is specified, verify combustion air and venting clearances are shown.
FBC-M 303FBC-FG 304
ElectricalRequired
- #01Equipotential bonding gridLife Safety
Verify a complete equipotential bonding grid is shown - pool shell reinforcement, metallic components within 5 feet, pool equipment, and perimeter bonding around the pool.
NEC 680.26 - #02GFCI protection for pool circuitsLife Safety
Verify GFCI protection is shown for pool equipment circuits, receptacles, and underwater luminaires.
NEC 680.5NEC 680.22NEC 680.23 - #03Underwater luminairesLife Safety
If underwater pool lights are included, verify they comply with NEC 680.23 (low-voltage preferred; line voltage requires specific installation).
NEC 680.23 - #04Equipment disconnect locationCode
Verify a disconnecting means is shown within sight of pool equipment, at least 5 feet horizontally from the inside wall of the pool.
NEC 680.12 - #05Underground wiring methodsCode
Verify burial depth and wiring method for underground pool circuits.
NEC 300.5NEC 680.10
PlumbingRequired
- #01Suction entrapment prevention (VGBA)Life Safety
Verify suction outlets comply with Virginia Graeme Baker Act requirements - dual main drains or unblockable single drain, ANSI/APSP-16 compliant covers.
ISPSC 31015 USC 8003 (VGBA) - #02Filtration and circulationCode
Verify filtration equipment is sized for pool volume and turnover rate is specified.
ISPSC 309 - #03Backflow prevention on auto-fillCode
If an auto-fill or auto-leveler is included, verify a backflow prevention device is specified on the water supply.
FBC-P 608ISPSC 312
Items marked Conditional review scope are non-blocking. Per FBC 107.3.5, plan review isn't required for these scopes — FCC reviews them when the building department requests it or the client wants the extra set of eyes.
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your FCC inspector will confirm which apply to your project. Call (772) 222-6679 with questions.
Building
Footing, Slab, UFER
Required- Rebar grid spacing and sizeCritical
Verify rebar size and spacing match approved plans
ISPSC 307.2FBC-R R506.2.4 - Pool excavation and formworkCritical
Verify pool shape, dimensions, and formwork match approved plans
ISPSC 307.2.1 - Pool depth verificationCritical
Confirm pool depth matches approved plans at shallow and deep ends
ISPSC 307.2 - Bonding grid perimeter wireCritical
Verify copper bonding wire is installed around pool perimeter per NEC
NEC 680.26 - Bonding grid to pool steel connectionsCritical
Verify bonding wire is connected to pool steel reinforcement
NEC 680.26(B) - Bonding of metallic components within 5 feetCritical
Verify all metallic components within 5 feet of pool edge are bonded
NEC 680.26(B) - Deck reinforcement layoutCritical
Verify deck rebar spacing, overlap, and placement per plans
ISPSC 306.1FBC-R R506.2.4 - Deck bonding wireCritical
Verify bonding wire is attached to reinforcement steel in deck area
NEC 680.26(B) - Plumbing and electrical conduit in place
Verify plumbing lines and electrical conduit are installed prior to pour
FBC-B 110.3
Plumbing
Underground Plumbing
Required- Pipe installation and supportCritical
Verify plumbing lines are properly installed and supported per plans
FBC-P 305.1 - Burial depthCritical
Verify underground pipe burial depth meets code minimum
FBC-P 305.5 - Pressure testCritical
Verify plumbing system holds required pressure test
FBC-P 312.2 - Distance from pool edgeCritical
Verify plumbing lines maintain required distance from pool edge per code
ISPSC 307.2 - Pipe sizing per plans
Verify pipe sizes match approved plans
FBC-P 604.1
Electrical
Underground Electrical
Required- Conduit and wiring installationCritical
Verify electrical conduit and wiring are properly installed per plans
NEC 680.11 - Burial depth verificationCritical
Verify conduit burial depth meets minimum code requirements
NEC 680.11(A) - Distance from pool edgeCritical
Verify electrical lines maintain required distance from pool edge
NEC 680.11 - Bonding connections at undergroundCritical
Verify bonding continuity at all underground electrical connections
NEC 680.26
Plumbing
Rough Plumbing
Required- Deck drain installationCritical
Verify deck drains are installed with proper slope away from pool
ISPSC 306.5.1 - Equipment pad plumbing connectionsCritical
Verify plumbing connections at pump, filter, and heater locations
ISPSC 308 - Suction outlet complianceCritical
Verify suction outlets meet entrapment avoidance requirements
ISPSC 307.1 - Deck slope and drainage direction
Verify deck slopes drain away from pool or toward deck drains
ISPSC 306.5
Electrical
Rough Electrical
Required- Equipment wiringCritical
Verify electrical wiring to pump, filter, heater per plans
NEC 680.21 - GFCI protectionCritical
Verify GFCI-protected outlets and circuits in pool area
NEC 680.22 - Receptacle locations and distancesCritical
Verify receptacle placement meets minimum distance requirements from pool
NEC 680.22(A) - Equipment bondingCritical
Verify bonding wire connections at all pool equipment
NEC 680.26(B)
Building
Final Building
RequiredTypical Final- Overall pool constructionCritical
Verify completed pool including decking matches approved plans
ISPSC 307.2 - Barrier heightCritical
Verify barrier is minimum 48 inches above grade on outside face
ISPSC 305.2.1 - Gate latch heightCritical
Verify gate latch release mechanism is at 54 inches from grade on pool side
ISPSC 305.3.3 - Gate self-closing and self-latchingCritical
Verify gates are self-closing and self-latching
ISPSC 305.3 - Barrier openingsCritical
Verify no opening in barrier allows passage of 4-inch sphere
ISPSC 305.2.2 - Deck condition and edges
Verify deck surface is slip-resistant with radiused edges
ISPSC 306.2ISPSC 306.8 - Equipment labels visible
Verify visible equipment labels on pumps, filters, heaters
FBC-B 110.3 - Emergency shut-off switch
Verify emergency shut-off switch is installed where required
NEC 680.12 - Pool alarm / dwelling-wall protection (R4501.17.1.9)Critical
Where any wall of the dwelling forms part of the pool barrier, verify ONE of three compliance methods is installed: exit alarms on all direct-access doors/windows, self-closing self-latching devices on all direct-access doors, or a certified in-pool alarm. Confirm method matches what was specified on approved plans. Skip if entire barrier is freestanding fence/screen with no dwelling wall participation.
FBC-R R4501.17.1.9
Electrical
Final Electrical
RequiredTypical Final- Pool light installationCritical
Verify pool lights are properly installed per plans and NEC
NEC 680.23 - Equipotential bonding completeCritical
Verify bonding of all required metallic components within 5 feet of pool
NEC 680.26(B) - GFCI protection operationalCritical
Verify all required circuits in pool area have GFCI protection and test
NEC 680.22 - Grounding connectionsCritical
Verify grounding connections at all pool equipment
NEC 680.25 - Disconnect switchCritical
Verify equipment disconnect switch is accessible and properly rated
NEC 680.12
Plumbing
Final Plumbing
RequiredTypical Final- Pump and filter operationCritical
Verify pump and filter are operational and properly installed
ISPSC 308 - Drain covers and suction safetyCritical
Verify main drain covers are compliant and properly secured
ISPSC 307.1 - Skimmer installation
Verify skimmers are properly installed and functional
ISPSC 307.2 - Heater installation
If heater present, verify installation per manufacturer specs
ISPSC 303.1.1 - Backflow preventionCritical
Verify backflow prevention device is installed on water supply
FBC-P 608.1
